Caltrans Logo

HOV Lanes on Rte 5 from Rte 170 to Rte 118

Description: In Los Angeles County, on Route 5 from Route 170 to Route 118. Construct one HOV lane in each direction and a direct HOV connection at the Route 5/170 interchange. (TCPR #41.2)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City
Zip Code
 
Senate District
18
Assembly District 39
Congressional District 29
 
Caltrans District
07
 
 
County/State Route Los Angeles 05
Postmile Begin/End 1.6 3.1
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  30      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Zareh Shahbazian 213-897-4255   zareh_shahbazian@dot.ca.gov
Design (PS&E) Phase
Caltrans Zareh Shahbazian 213-897-4255   zareh_shahbazian@dot.ca.gov
Right of Way Phase
Caltrans Zareh Shahbazian 213-897-4255   zareh_shahbazian@dot.ca.goc
Construction Phase
Caltrans Zareh Shahbazian 213-897-4255   zareh_shahbazian@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $41,801 $41,801
SLPP
$0 $0 $0
SLPP
$40,000 $-14,925 $25,075
Non-bond Funding
State/Federal*
$102,106 $373 $102,479
Local**
$93,400 $-30,954 $62,446
 
Total**** $235,506 $-3,705 $231,801

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $1,341 $1,341 $1,249 $1,249 $92
Design(PS&E)
$19,838 $12,944 $32,782 $28,072 $28,072 $4,710
Right of Way
$43,800 $13,176 $56,976 $57,210 $57,210 $-234
Construction
$187,288 $-46,586 $140,702 $141,625 $141,625 $-923
 
Total* $235,506 $-3,705 $231,801 $196,918 $196,918 $34,883

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100  01/25/1998 

12/29/2000 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

10/01/2008 
100  01/02/2001 

10/16/2009 


-13 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100  08/01/2001 

03/16/2009 


Begin Construction Phase

End Construction Phase
 

 
 

 
05/06/2010 

12/02/2013 
06/28/2013 

07/25/2016 
-38 

-32 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
07/27/2016 

12/28/2020 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 30

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.