Rte 50 Missouri Flat Interchange

Description: In Placerville, on Route 50 at Missouri Flat Road. Construct interchange Improvements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City Placerville
Zip Code 95667
 
Senate District
01
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
 
County/State Route El Dorado 50
Postmile Begin/End 14.4 15.8
Project Benefits
 Benefit Baseline Actual
Additional Auxiliary Lane Miles  2      
Separated Bike/Pedestrian Paths  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
El Dorado County Adam Bane 916-358-3552   Adam.Bane@edcgov.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $27,506 $27,506
Non-bond Funding
State/Federal*
$0 $5,000 $5,000
Local**
$0 $2,225 $2,225
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $34,731 $34,731

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $70 $70 $174 $174 $-104
Design(PS&E)
$0 $1,405 $1,405 $2,225 $2,225 $-820
Right of Way
$0 $750 $750 $336 $336 $414
Construction
$0 $32,506 $32,506 $37,537 $39,851 $-7,345
 
Total* $0 $34,731 $34,731 $35,099 $37,413 $-2,682

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
12/01/2000 

04/14/2005 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
09/28/2007 

07/07/2009 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
11/01/2005 

06/11/2009 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
11/09/2009 

10/01/2015 
 

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
10/01/2015 

10/31/2018 
 

 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Auxiliary Lane Miles 2
Separated Bike/Pedestrian Paths 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.