Rte 50 Missouri Flat Interchange |
Description: In Placerville, on Route 50 at Missouri Flat Road. Construct interchange Improvements.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
El Dorado |
City | Placerville |
Zip Code | 95667 |
Senate District |
01 |
Assembly District | 04 |
Congressional District | 04 |
Caltrans District |
03 |
County/State Route | El Dorado 50 |
Postmile Begin/End | 14.4 15.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 2 | |
Separated Bike/Pedestrian Paths | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
El Dorado County | Adam Bane | 916-358-3552 | Adam.Bane@edcgov.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $27,506 | $27,506 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $5,000 | $5,000 | ||||
Local** |
$0 | $2,225 | $2,225 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $34,731 | $34,731 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $70 | $70 | $174 | $174 | $-104 | |
Design(PS&E) |
$0 | $1,405 | $1,405 | $2,225 | $2,225 | $-820 | |
Right of Way |
$0 | $750 | $750 | $336 | $336 | $414 | |
Construction |
$0 | $32,506 | $32,506 | $37,537 | $39,851 | $-7,345 | |
Total* | $0 | $34,731 | $34,731 | $35,099 | $37,413 | $-2,682 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
12/01/2000 04/14/2005 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
09/28/2007 07/07/2009 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
11/01/2005 06/11/2009 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
11/09/2009 10/01/2015 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
10/01/2015 10/31/2018 |
0 | |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 2 | |
Separated Bike/Pedestrian Paths | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.