VEN-118 Widening, Tapo Cyn to LA Co Line |
Description: In Simi Valley, from Tapo Canyon Road to the Los Angeles county line. Add one mixed flow lane (westbound) and add one lane between Tapo Canyon Road and Tapo Street (eastbound).
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Ventura |
City | Simi Valley |
Zip Code | 93062 |
Senate District |
17, 19 |
Assembly District | 37, 38 |
Congressional District | 24, 30 |
Caltrans District |
07 |
County/State Route | Ventura 118 |
Postmile Begin/End | 27 32.5 |
County/State Route | Ventura 118 |
Postmile Begin/End | 27.3 32.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | 1 | |
Lane Miles Added (HOV) | 11.00 | |
Lane Miles Added (Mixed) | 7.784 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Carlos Montez | 213-897-9116 | carlos_montez@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Derek Higa | 213-897-0394 | derek_Higa@dot.ca.gov | |
Right of Way Phase |
Caltrans | Dan Murdoch | 213-897-1816 | dan_murdoch@dot.ca.gov | |
Construction Phase |
Caltrans | Joseph Tehrani | 805-480-4982 | joseph_Tehrani@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Reza Fateh | 213-897-8316 | Reza_Fateh@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $12,472 | $12,472 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $7,927 | $7,927 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $20,399 | $20,399 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $1,395 | $1,395 | $1,522 | $1,522 | $-127 | |
Right of Way |
$0 | $25 | $25 | $0 | $43 | $-18 | |
Construction |
$0 | $18,979 | $18,979 | $18,226 | $18,258 | $721 | |
Total* | $0 | $20,399 | $20,399 | $13,242 | $13,317 | $7,082 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/06/2000 02/28/2001 |
|
03/06/2000 02/28/2001 |
100 | 03/06/2000 02/28/2001 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/22/2007 05/25/2008 |
|
11/01/2007 02/18/2009 |
100 | 11/01/2007 02/18/2009 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
11/15/2007 04/20/2008 |
|
01/14/2008 08/05/2011 |
100 | 01/14/2008 08/05/2011 |
0 0 |
Begin Construction Phase
End Construction Phase |
10/15/2008 08/05/2010 |
11/24/2009 06/15/2011 |
11/24/2009 08/05/2011 |
100 | 11/24/2009 08/05/2011 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/01/2011 12/01/2011 |
08/05/2011 |
08/05/2011 02/29/2012 |
75 | 08/05/2011 02/29/2012 |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | 1 | |
Lane Miles Added (HOV) | 11.00 | |
Lane Miles Added (Mixed) | 7.784 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$12,472,000 |
Actual Expenditures: |
$11,719,000 |
Status as of December 31, 2023.