Caltrans Logo

VEN-118 Widening, Tapo Cyn to LA Co Line

Description: In Simi Valley, from Tapo Canyon Road to the Los Angeles county line. Add one mixed flow lane (westbound) and add one lane between Tapo Canyon Road and Tapo Street (eastbound).

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Simi Valley
Zip Code 93062
 
Senate District
17, 19
Assembly District 37, 38
Congressional District 24, 30
 
Caltrans District
07
 
 
County/State Route Ventura 118
Postmile Begin/End 27 32.5
 
County/State Route Ventura 118
Postmile Begin/End 27.3 32.6
Project Benefits
 Benefit Baseline Actual
Increase in Throughput  1      
Lane Miles Added (HOV)  11.00      
Lane Miles Added (Mixed)      7.784  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Carlos Montez 213-897-9116   carlos_montez@dot.ca.gov
Design (PS&E) Phase
Caltrans Derek Higa 213-897-0394   derek_Higa@dot.ca.gov
Right of Way Phase
Caltrans Dan Murdoch 213-897-1816   dan_murdoch@dot.ca.gov
Construction Phase
Caltrans Joseph Tehrani 805-480-4982   joseph_Tehrani@dot.ca.gov
 
Corridor System Management Plan
Caltrans Reza Fateh 213-897-8316   Reza_Fateh@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $12,472 $12,472
Non-bond Funding
State/Federal*
$0 $7,927 $7,927
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $20,399 $20,399

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $1,395 $1,395 $1,522 $1,522 $-127
Right of Way
$0 $25 $25 $0 $43 $-18
Construction
$0 $18,979 $18,979 $18,226 $18,258 $721
 
Total* $0 $20,399 $20,399 $13,242 $13,317 $7,082

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/06/2000 

02/28/2001 
 

 
03/06/2000 

02/28/2001 
100  03/06/2000 

02/28/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/22/2007 

05/25/2008 
 

 
11/01/2007 

02/18/2009 
100  11/01/2007 

02/18/2009 


Begin Right of Way Phase

End Right of Way Phase
11/15/2007 

04/20/2008 
 

 
01/14/2008 

08/05/2011 
100  01/14/2008 

08/05/2011 


Begin Construction Phase

End Construction Phase
10/15/2008 

08/05/2010 
11/24/2009 

06/15/2011 
11/24/2009 

08/05/2011 
100  11/24/2009 

08/05/2011 


Begin Closeout Phase

End Closeout Phase
02/01/2011 

12/01/2011 
08/05/2011 

 
08/05/2011 

02/29/2012 
75  08/05/2011 

02/29/2012 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput 1
Lane Miles Added (HOV) 11.00
Lane Miles Added (Mixed) 7.784

Bond Funding Cost
Adopted:
$0
Current Approved:
$12,472,000
Actual Expenditures:
$11,719,000

 

Status as of December 31, 2023.