Brawley Bypass (Route 78/111 Expressway)

Description: In and near Brawley on Route 78 from Route 86 to 0.6 km east of Hovley Road and on Route 86 from 0.5km south to 0.1km north of Fredricks Road. Construct new 4 lane divided expressw

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City Brawley
Zip Code 92227
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
 
County/State Route Imperial 078
Postmile Begin/End R  9.2 R  12.1
Project Benefits
 Benefit Baseline Actual
Increase in Throughput  3      
Lane Miles Added (Mixed)  3      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Sam Amen (619) 718-7835   Sam_Amen@dot.ca.gov
Design (PS&E) Phase
Caltrans Sam Amen (619) 718-7835   Sam_Amen@dot.ca.gov
Right of Way Phase
Caltrans Sam Amen (619) 718-7835   Sam_Amen@dot.ca.gov
Construction Phase
Caltrans Sam Amen (619) 718-7835   Sam_Amen@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $11,944 $11,944
IIP Augmentation
$0 $4,444 $4,444
TCIF
$0 $43,122 $43,122
Non-bond Funding
State/Federal*
$0 $26,275 $26,275
Local**
$0 $908 $908
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $86,693 $86,693

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $1,206 $1,206 $340 $340 $866
Design(PS&E)
$0 $6,500 $6,500 $5,967 $5,967 $533
Right of Way
$0 $34,957 $34,957 $15,000 $15,000 $19,957
Construction
$0 $44,030 $44,030 $43,090 $43,090 $940
 
Total* $0 $86,693 $86,693 $64,398 $64,398 $22,296

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
11/30/2010 

12/10/2012 
100  11/30/2010 

12/10/2012 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
 

 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput 3
Lane Miles Added (Mixed) 3

Bond Funding Cost
Adopted:
$0
Current Approved:
$43,122,000
Actual Expenditures:
$42,121,879

Click to view the Final Audit Report

 

Status as of December 31, 2023.