Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Brawley Bypass (Route 78/111 Expressway) |
Description: In and near Brawley on Route 78 from Route 86 to 0.6 km east of Hovley Road and on Route 86 from 0.5km south to 0.1km north of Fredricks Road. Construct new 4 lane divided expressw
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Imperial |
City | Brawley |
Zip Code | 92227 |
Senate District |
40 |
Assembly District | 80 |
Congressional District | 51 |
Caltrans District |
11 |
County/State Route | Imperial 078 |
Postmile Begin/End | R 9.2 R 12.1 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | 3 | |
Lane Miles Added (Mixed) | 3 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Sam Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Sam Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov | |
Right of Way Phase |
Caltrans | Sam Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov | |
Construction Phase |
Caltrans | Sam Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $11,944 | $11,944 | ||||
IIP Augmentation |
$0 | $4,444 | $4,444 | ||||
TCIF |
$0 | $43,122 | $43,122 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $26,275 | $26,275 | ||||
Local** |
$0 | $908 | $908 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $86,693 | $86,693 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $1,206 | $1,206 | $340 | $340 | $866 | |
Design(PS&E) |
$0 | $6,500 | $6,500 | $5,967 | $5,967 | $533 | |
Right of Way |
$0 | $34,957 | $34,957 | $15,000 | $15,000 | $19,957 | |
Construction |
$0 | $44,030 | $44,030 | $43,090 | $43,090 | $940 | |
Total* | $0 | $86,693 | $86,693 | $64,398 | $64,398 | $22,296 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
11/30/2010 12/10/2012 |
100 | 11/30/2010 12/10/2012 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | 3 | |
Lane Miles Added (Mixed) | 3 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$43,122,000 |
Actual Expenditures: |
$42,121,879 |
Status as of December 31, 2023.