North Old Stage Road Project |
Description: Near Weed and Mount Shasta, on North Old Stage Road from Abrams Lake Road to College Avenue, all of Lassen Lane, and all of Abrams Lake Road. Overlay.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Siskiyou |
City | Mount Shasta |
Zip Code | 96067 |
Senate District |
04 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
02 |
County/State Route | Siskiyou 0 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) | 9.5 | 9.5 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Siskiyou County | Scott Waite | (530) 842-8275 | swaite@co.siskiyou.ca.us | |
Design (PS&E) Phase |
Siskiyou County | Scott Waite | (530) 842-8275 | swaite@co.siskiyou.ca.us | |
Right of Way Phase |
|||||
Construction Phase |
Siskiyou County | Scott Waite | (530) 842-8275 | swaite@co.siskiyou.ca.us | |
Corridor System Management Plan |
Siskiyou County | Scott Waite | (530) 842-8275 | swaite@co.siskiyou.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $3,000 | $3,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $61 | $61 | ||||
Local** |
$0 | $40 | $40 | ||||
Total**** | $0 | $3,101 | $3,101 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $20 | $20 | $0 | $0 | $20 | |
Design(PS&E) |
$0 | $80 | $80 | $36 | $36 | $44 | |
Right of Way |
$0 | $1 | $1 | $0 | $0 | $1 | |
Construction |
$0 | $3,000 | $3,000 | $2,868 | $2,868 | $132 | |
Total* | $0 | $3,101 | $3,101 | $2,904 | $2,904 | $197 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/14/2009 11/30/2009 |
|
11/10/2009 11/30/2012 |
100 | 05/14/2010 09/28/2010 |
-6 26 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | 10/11/2010 11/23/2010 |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) | 9.5 | 9.5 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$3,066,000 |
Actual Expenditures: |
$2,819,922 |
Status as of December 31, 2023.