North Old Stage Road Project

Description: Near Weed and Mount Shasta, on North Old Stage Road from Abrams Lake Road to College Avenue, all of Lassen Lane, and all of Abrams Lake Road. Overlay.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Siskiyou
City Mount Shasta
Zip Code 96067
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
 
County/State Route Siskiyou 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Rehabilitated Lane Miles (miles)  9.5    9.5  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Siskiyou County Scott Waite (530) 842-8275   swaite@co.siskiyou.ca.us
Design (PS&E) Phase
Siskiyou County Scott Waite (530) 842-8275   swaite@co.siskiyou.ca.us
Right of Way Phase
 
Construction Phase
Siskiyou County Scott Waite (530) 842-8275   swaite@co.siskiyou.ca.us
 
Corridor System Management Plan
Siskiyou County Scott Waite (530) 842-8275   swaite@co.siskiyou.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $3,000 $3,000
Non-bond Funding
State/Federal*
$0 $61 $61
Local**
$0 $40 $40
 
Total**** $0 $3,101 $3,101

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $20 $20 $0 $0 $20
Design(PS&E)
$0 $80 $80 $36 $36 $44
Right of Way
$0 $1 $1 $0 $0 $1
Construction
$0 $3,000 $3,000 $2,868 $2,868 $132
 
Total* $0 $3,101 $3,101 $2,904 $2,904 $197

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/14/2009 

11/30/2009 
 

 
11/10/2009 

11/30/2012 
100  05/14/2010 

09/28/2010 
-6 

26 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
10/11/2010 

11/23/2010 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rehabilitated Lane Miles (miles) 9.5 9.5

Bond Funding Cost
Adopted:
$0
Current Approved:
$3,066,000
Actual Expenditures:
$2,819,922

 

Status as of December 31, 2023.