N. State St Improvements Phase I

Description: Near Ukiah, on North State Street from south of Orr Spring Road to the Hensley Creek intersection. Widen and install a continuous left turn lane and bicycle lanes, and instersecti

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mendocino
City Ukiah
Zip Code 95482
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
 
County/State Route Mendocino 104
Postmile Begin/End 0.6 2.3
Project Benefits
 Benefit Baseline Actual
Increase in Throughput  1      
Separated Bike/Pedestrian Paths  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Mendocino County Department of Transportation Howard Dashiell 7074634363   dashielh@co.mendocino.ca.us
Design (PS&E) Phase
Mendocino County Department of Transportation Howard Dashiell 7074634363   dashielh@co.mendocino.ca.us
Right of Way Phase
Mendocino County Department of Transportation Howard Dashiell 7074634363   dashielh@co.mendocino.ca.us
Construction Phase
Mendocino County Department of Transportation Howard Dashiell 7074634363   dashielh@co.mendocino.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$7,690 $0 $7,690
Non-bond Funding
State/Federal*
$919 $0 $919
 
Total**** $8,609 $0 $8,609

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$576 $0 $576 $586 $586 $-10
Design(PS&E)
$74 $0 $74 $234 $234 $-161
Right of Way
$167 $0 $167 $195 $195 $-28
Construction
$7,792 $0 $7,792 $8,545 $8,545 $-753
 
Total* $8,609 $0 $8,609 $9,560 $9,560 $-951

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
09/07/2002 

 
100   

07/14/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
07/14/2008 

 
100   

11/03/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
11/03/2008 

10/30/2009 
100  10/30/2009 

08/24/2009 
-12 

Begin Construction Phase

End Construction Phase
08/28/2008 

02/28/2009 
 

 
08/24/2009 

07/30/2010 
100  07/30/2010 

06/01/2011 
-11 

-10 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
06/01/2011 

01/31/2012 
100  01/31/2012 

 
-8 

????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput 1
Separated Bike/Pedestrian Paths 1

Bond Funding Cost
Adopted:
$7,690,000
Current Approved:
$3,845,000
Actual Expenditures:
$3,845,000

 

Status as of December 31, 2023.