Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
North Milliken Grade Separation at UPRR Lines |
Description: In Ontario, on North Milliken Avenue. Construct a grade separation for UPRR lines (Alameda Corridor East).
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Ontario |
Zip Code | 91764 |
Senate District |
32 |
Assembly District | 61 |
Congressional District | 43 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | .5 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Ontario, City of | Tom Danna | (909) 395-2387 | tdanna@ci.ontario.ca.us | |
Design (PS&E) Phase |
Ontario, City of | Tom Danna | (909) 395-2387 | tdanna@ci.ontario.ca.us | |
Right of Way Phase |
Ontario, City of | Tom Danna | (909) 395-2387 | tdanna@ci.ontario.ca.us | |
Construction Phase |
San Bernardino Associated Governments (SANBAG) | Philip Chu | (909) 889-8611 | pchu@sanbag.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$33,768 | $11,321 | $45,089 | ||||
Non-bond Funding | |||||||
State/Federal* |
$5,000 | $3,207 | $8,207 | ||||
Local** |
$8,444 | $12,243 | $20,687 | ||||
Private*** |
$2,161 | $-2,161 | $0 | ||||
Total**** | $49,373 | $24,610 | $73,983 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $557 | $557 | $557 | $557 | $0 | |
Design(PS&E) |
$0 | $4,000 | $4,000 | $2,990 | $2,990 | $1,010 | |
Right of Way |
$0 | $5,000 | $5,000 | $4,650 | $4,650 | $350 | |
Construction |
$49,373 | $15,053 | $64,426 | $39,544 | $39,544 | $24,882 | |
Total* | $49,373 | $24,610 | $73,983 | $47,741 | $47,741 | $26,242 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
11/03/2010 05/30/2011 |
|
11/03/2010 11/30/2013 |
100 | 11/03/2010 11/30/2013 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | 12/01/2013 02/26/2016 |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | .5 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.