Caltrans Logo

North Milliken Grade Separation at UPRR Lines

Description: In Ontario, on North Milliken Avenue. Construct a grade separation for UPRR lines (Alameda Corridor East).

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Ontario
Zip Code 91764
 
Senate District
32
Assembly District 61
Congressional District 43
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  .5      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Ontario, City of Tom Danna (909) 395-2387   tdanna@ci.ontario.ca.us
Design (PS&E) Phase
Ontario, City of Tom Danna (909) 395-2387   tdanna@ci.ontario.ca.us
Right of Way Phase
Ontario, City of Tom Danna (909) 395-2387   tdanna@ci.ontario.ca.us
Construction Phase
San Bernardino Associated Governments (SANBAG) Philip Chu (909) 889-8611   pchu@sanbag.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$33,768 $11,321 $45,089
Non-bond Funding
State/Federal*
$5,000 $3,207 $8,207
Local**
$8,444 $12,243 $20,687
Private***
$2,161 $-2,161 $0
 
Total**** $49,373 $24,610 $73,983

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $557 $557 $557 $557 $0
Design(PS&E)
$0 $4,000 $4,000 $2,990 $2,990 $1,010
Right of Way
$0 $5,000 $5,000 $4,650 $4,650 $350
Construction
$49,373 $15,053 $64,426 $39,544 $39,544 $24,882
 
Total* $49,373 $24,610 $73,983 $47,741 $47,741 $26,242

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/03/2010 

05/30/2011 
 

 
11/03/2010 

11/30/2013 
100  11/03/2010 

11/30/2013 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
12/01/2013 

02/26/2016 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) .5

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.