Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
OWENS GORGE ROAD REHABILITATION |
Description: Near Toms Place on Ownes Gorge Rd between Rt 395 and the end of existing pavement.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Mono |
City | Bishop |
Zip Code | 93514 |
Senate District |
01 |
Assembly District | 25 |
Congressional District | 25 |
Caltrans District |
09 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Mono County | Garrett Higerd | (760) 932-5457 | ghigerd@mono.ca.ogv | |
Design (PS&E) Phase |
Mono County | Garrett Higerd | (760) 932-5457 | ghigerd@mono.ca.ogv | |
Right of Way Phase |
Mono County | Garrett Higerd | (760) 932-5457 | ghigerd@mono.ca.ogv | |
Construction Phase |
Mono County | Garrett Higerd | (760) 932-5457 | ghigerd@mono.ca.ogv | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$1,619 | $0 | $1,619 | ||||
Non-bond Funding | |||||||
Local** |
$101 | $0 | $101 | ||||
Total**** | $1,720 | $0 | $1,720 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$28 | $0 | $28 | $0 | $0 | $28 | |
Design(PS&E) |
$18 | $0 | $18 | $0 | $0 | $18 | |
Right of Way |
$55 | $0 | $55 | $0 | $0 | $55 | |
Construction |
$1,619 | $0 | $1,619 | $0 | $0 | $1,619 | |
Total* | $1,720 | $0 | $1,720 | $0 | $0 | $1,720 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/2002 06/30/2003 |
12/08/2010 12/08/2010 |
06/08/2006 06/01/2008 |
100 | 06/08/2006 04/25/2008 |
0 1 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2002 06/30/2004 |
12/08/2010 12/08/2010 |
06/26/2008 09/03/2010 |
100 | 06/26/2008 09/03/2010 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2002 06/30/2004 |
12/08/2010 12/08/2010 |
06/28/2008 06/30/2010 |
100 | 06/28/2008 06/30/2010 |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2003 06/30/2005 |
12/08/2010 12/08/2010 |
04/20/2011 06/30/2011 |
100 | 05/24/2011 09/30/2011 |
-1 -3 |
Begin Closeout Phase
End Closeout Phase |
|
12/08/2010 12/08/2010 |
07/01/2011 12/31/2011 |
100 | 10/01/2011 01/30/2012 |
-3 -1 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,619,000 |
Current Approved: |
$1,619,000 |
Actual Expenditures: |
$1,572,830 |
Status as of December 31, 2023.