Caltrans Logo

Simpson Lane Intersection

Description: In Mendocino County near Fort Bragg at the Intersection of Simpson Lane and State Route 1.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mendocino
City Fort Bragg
Zip Code 95437
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
 
County/State Route Mendocino 1
Postmile Begin/End 59.3 59.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      554  
Increase in Throughput  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Steven Blair (707)441-5899   Steven_Blair@dot.ca.gov
Design (PS&E) Phase
Caltrans Steven Blair (707)441-5899   Steven_Blair@dot.ca.gov
Right of Way Phase
Caltrans Steven Blair (707)441-5899   Steven_Blair@dot.ca.gov
Construction Phase
Caltrans Steven Blair (707)441-5899   Steven_Blair@dot.ca.gov
 
Corridor System Management Plan
Caltrans Steven Blair (707)441-5899   Steven_Blair@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$495 $0 $495
Non-bond Funding
State/Federal*
$0 $1,000 $1,000
Local**
$0 $200 $200
Non Budgeted ETC
$0 $0 $0
 
Total**** $495 $1,200 $1,695

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $643 $643 $-643
Design(PS&E)
$0 $0 $0 $922 $922 $-922
Right of Way
$0 $0 $0 $1,075 $1,128 $-1,128
Construction
$495 $1,200 $1,695 $2,003 $2,065 $-370
 
Total* $495 $1,200 $1,695 $4,642 $4,758 $-3,063

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

05/18/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

10/04/2010 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

09/21/2010 


Begin Construction Phase

End Construction Phase
05/12/2011 

01/01/2012 
 

 
05/12/2011 

01/01/2012 
05/12/2011 

01/03/2012 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
05/14/2012 

07/15/2013 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 554
Increase in Throughput 1

Bond Funding Cost
Adopted:
$495,000
Current Approved:
$1,695,000
Actual Expenditures:
$1,659,000

 

Status as of December 31, 2023.