Willits Bypass

Description: Near Willits (Willits Bypass), Haehl Creek overhead to Reynolds Highway. Construct 2 lane highway on new alignment.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Mendocino
City Willits
Zip Code 95490
 
Senate District
02
Assembly District 01
Congressional District 01
 
Caltrans District
01
 
 
County/State Route Mendocino 101
Postmile Begin/End 43.5 51.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  750    750  
Increase in Throughput  x      
Lane Miles Added (Mixed)  15    0  
Peak Period Time Savings (minutes)  10-15    15  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Jen Buck (707)441-5877   jen.buck@dot.ca.gov
Design (PS&E) Phase
Caltrans Jen Buck (707)441-5877   jen.buck@dot.ca.gov
Right of Way Phase
Caltrans Jen Buck (707)441-5877   jen.buck@dot.ca.gov
Construction Phase
Caltrans Jen Buck (707)441-5877   jen.buck@dot.ca.gov
 
Corridor System Management Plan
Caltrans Jen Buck (707)441-5877   jen.buck@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$20,327 $0 $20,327
IIP Augmentation
$115,184 $0 $115,184
Non-bond Funding
State/Federal*
$71,066 $138,782 $209,848
Local**
$6,250 $0 $6,250
Non Budgeted ETC
$0 $0 $0
 
Total**** $212,827 $138,782 $351,609

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$9,865 $2,777 $12,642 $9,865 $9,865 $2,777
Design(PS&E)
$35,398 $4,827 $40,225 $40,225 $42,667 $-2,442
Right of Way
$12,035 $24,940 $36,975 $36,878 $39,940 $-2,965
Construction
$155,529 $106,238 $261,767 $257,262 $384,569 $-122,802
 
Total* $212,827 $138,782 $351,609 $344,231 $477,041 $-125,432

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/1998 

12/31/2006 
 

 
07/01/1998 

12/18/2006 
100  07/01/1998 

12/18/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

07/15/2009 
 

 
 

02/22/2011 
100   

02/22/2012 


-12 
Begin Right of Way Phase

End Right of Way Phase
 

07/01/2009 
 

 
 

05/28/2010 
93  12/22/2005 

05/28/2010 


Begin Construction Phase

End Construction Phase
01/01/2010 

10/01/2014 
 

 
07/26/2012 

12/22/2016 
07/26/2012 

12/22/2016 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
12/31/2027 

09/01/2029 
50  12/31/2027 

09/01/2029 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 750 750
Increase in Throughput x
Lane Miles Added (Mixed) 15 0
Peak Period Time Savings (minutes) 10-15 15

Bond Funding Cost
Adopted:
$135,511,000
Current Approved:
$131,125,000
Actual Expenditures:
$131,125,000

 

Status as of December 31, 2023.