19th Avenue Interchange

Description: In Lemoore, on Route 198 at 19th Avenue. Construct interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Lemoore
Zip Code 93245
 
Senate District
16
Assembly District 33
Congressional District 20
 
Caltrans District
06
 
 
County/State Route Kings 198
Postmile Begin/End R  8.6 R  10.1
Project Benefits
 Benefit Baseline Actual
Increase in Throughput  1 IC      
Peak Period Time Savings (minutes)      xxx  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Anand Kapoor (559) 243-3588   anand_kapoor@dot.ca.gov
Design (PS&E) Phase
Caltrans Anand Kapoor (559) 243-3588   anand_kapoor@dot.ca.gov
Right of Way Phase
Caltrans Anand Kapoor (559) 243-3588   anand_kapoor@dot.ca.gov
Construction Phase
Caltrans Anand Kapoor (559) 243-3588   anand_kapoor@dot.ca.gov
 
Corridor System Management Plan
Caltrans Anand Kapoor (559) 243-3588   anand_kapoor@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$21,226 $0 $21,226
Non-bond Funding
State/Federal*
$12,126 $0 $12,126
 
Total**** $33,352 $0 $33,352

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1,471 $0 $1,471 $1,477 $1,477 $-6
Design(PS&E)
$1,630 $0 $1,630 $4,587 $4,587 $-2,957
Right of Way
$6,255 $0 $6,255 $8,748 $8,748 $-2,493
Construction
$23,996 $0 $23,996 $23,671 $23,671 $325
 
Total* $33,352 $0 $33,352 $38,483 $38,483 $-5,131

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

06/20/2005 
 

 
 

06/20/2005 
 

06/20/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

12/15/2010 
 

 
 

12/23/2011 
 

12/23/2011 


Begin Right of Way Phase

End Right of Way Phase
 

12/05/2010 
 

 
03/05/2009 

 
100  03/05/2009 

 


Begin Construction Phase

End Construction Phase
12/15/2010 

03/15/2014 
 

 
10/24/2012 

05/06/2015 
10/24/2012 

05/06/2015 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
05/06/2015 

07/15/2018 
07/15/2018 

11/21/2021 
-39 

-41 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Throughput 1 IC
Peak Period Time Savings (minutes) xxx

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.