19th Avenue Interchange |
Description: In Lemoore, on Route 198 at 19th Avenue. Construct interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kings |
City | Lemoore |
Zip Code | 93245 |
Senate District |
16 |
Assembly District | 33 |
Congressional District | 20 |
Caltrans District |
06 |
County/State Route | Kings 198 |
Postmile Begin/End | R 8.6 R 10.1 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | 1 IC | |
Peak Period Time Savings (minutes) | xxx |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Anand Kapoor | (559) 243-3588 | anand_kapoor@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Anand Kapoor | (559) 243-3588 | anand_kapoor@dot.ca.gov | |
Right of Way Phase |
Caltrans | Anand Kapoor | (559) 243-3588 | anand_kapoor@dot.ca.gov | |
Construction Phase |
Caltrans | Anand Kapoor | (559) 243-3588 | anand_kapoor@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Anand Kapoor | (559) 243-3588 | anand_kapoor@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$21,226 | $0 | $21,226 | ||||
Non-bond Funding | |||||||
State/Federal* |
$12,126 | $0 | $12,126 | ||||
Total**** | $33,352 | $0 | $33,352 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1,471 | $0 | $1,471 | $1,477 | $1,477 | $-6 | |
Design(PS&E) |
$1,630 | $0 | $1,630 | $4,587 | $4,587 | $-2,957 | |
Right of Way |
$6,255 | $0 | $6,255 | $8,748 | $8,748 | $-2,493 | |
Construction |
$23,996 | $0 | $23,996 | $23,671 | $23,671 | $325 | |
Total* | $33,352 | $0 | $33,352 | $38,483 | $38,483 | $-5,131 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/20/2005 |
|
06/20/2005 |
0 | 06/20/2005 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/15/2010 |
|
12/23/2011 |
0 | 12/23/2011 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/05/2010 |
|
03/05/2009 |
100 | 03/05/2009 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/15/2010 03/15/2014 |
|
10/24/2012 05/06/2015 |
0 | 10/24/2012 05/06/2015 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
05/06/2015 07/15/2018 |
0 | 07/15/2018 11/21/2021 |
-39 -41 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Throughput | 1 IC | |
Peak Period Time Savings (minutes) | xxx |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.