San Mateo County Smart Corridor - Local |
Description: Located between Route 101 and Route 82 corridor, from Whipple Avenue to Route 380 on major arterials. Install traffic signal improvements, CCTV's, trailblazer signs, and vehicle detection systems.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Mateo |
Zip Code | 94403 |
Senate District |
11 |
Assembly District | 21 |
Congressional District | 14 |
Caltrans District |
04 |
County/State Route | San Mateo 82 |
Postmile Begin/End | 0 19 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 20 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
San Mateo City/County Government of Association | John Hoang | (510) 908-2622 | jhoang@smcgov.org | |
Design (PS&E) Phase |
San Mateo City/County Government of Association | John Hoang | (510) 908-2622 | jhoang@smcgov.org | |
Right of Way Phase |
San Mateo City/County Government of Association | John Hoang | (510) 908-2622 | jhoang@smcgov.org | |
Construction Phase |
San Mateo City/County Government of Association | John Hoang | (510) 908-2622 | jhoang@smcgov.org | |
Corridor System Management Plan |
Caltrans | Jerry Claussenius | (510) 908-2622 | jerry.claussenius@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $5,270 | $5,270 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $3,000 | $3,000 | ||||
Local** |
$0 | $2,299 | $2,299 | ||||
Total**** | $0 | $10,569 | $10,569 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $400 | $400 | $0 | $0 | $400 | |
Design(PS&E) |
$0 | $3,669 | $3,669 | $0 | $0 | $3,669 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$0 | $6,500 | $6,500 | $0 | $0 | $6,500 | |
Total* | $0 | $10,569 | $10,569 | $0 | $0 | $10,569 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
|
100 | 07/15/2012 08/01/2014 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | 08/01/2014 06/30/2017 |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 20 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.