San Mateo County Smart Corridor - State |
Description: In San Mateo County, located within state right of way along SR 82 and at ramps to US 101, from Whipple Avenue to Route 380. This project will construct traffic signal improvements, CCTVs, traillazer
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Mateo |
Zip Code | 94403 |
Senate District |
08 |
Assembly District | 12, 19, 21 |
Congressional District | 12, 14 |
Caltrans District |
04 |
County/State Route | San Mateo 82 |
Postmile Begin/End | 0 19 |
County/State Route | San Mateo 82 |
Postmile Begin/End | 0 19 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 20 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
San Mateo City/County Government of Association | John Hoang | (910) 908-2622 | jhoang@smcgov.org | |
Design (PS&E) Phase |
San Mateo City/County Government of Association | John Hoang | (910) 908-2622 | jhoang@smcgov.org | |
Right of Way Phase |
Caltrans | Jerry Claussenius | (910) 908-2622 | jerry.claussenius@dot.ca.gov | |
Construction Phase |
Caltrans | Jerry Claussenius | (910) 908-2622 | jerry.claussenius@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Jerry Claussenius | (910) 908-2622 | jerry.claussenius@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $2,730 | $2,730 | ||||
TLSP |
$0 | $5,545 | $5,545 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$0 | $50 | $50 | ||||
Total**** | $0 | $8,325 | $8,325 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $2,392 | $2,392 | $-2,392 | |
Design(PS&E) |
$0 | $0 | $0 | $2,284 | $2,284 | $-2,284 | |
Right of Way |
$0 | $50 | $50 | $16 | $16 | $34 | |
Construction |
$0 | $8,275 | $8,275 | $9,321 | $9,321 | $-1,046 | |
Total* | $0 | $8,325 | $8,325 | $14,013 | $14,013 | $-5,688 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
02/22/2010 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
01/26/2011 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
04/25/2012 07/22/2016 |
0 | 04/25/2012 07/22/2016 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
07/22/2017 12/30/2016 |
0 | 12/01/2017 06/29/2018 |
-4 -18 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 20 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.