San Mateo County Smart Corridor - State

Description: In San Mateo County, located within state right of way along SR 82 and at ramps to US 101, from Whipple Avenue to Route 380. This project will construct traffic signal improvements, CCTVs, traillazer

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Mateo
Zip Code 94403
 
Senate District
08
Assembly District 12, 19, 21
Congressional District 12, 14
 
Caltrans District
04
 
 
County/State Route San Mateo 82
Postmile Begin/End 0 19
 
County/State Route San Mateo 82
Postmile Begin/End 0 19
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
San Mateo City/County Government of Association John Hoang (910) 908-2622   jhoang@smcgov.org
Design (PS&E) Phase
San Mateo City/County Government of Association John Hoang (910) 908-2622   jhoang@smcgov.org
Right of Way Phase
Caltrans Jerry Claussenius (910) 908-2622   jerry.claussenius@dot.ca.gov
Construction Phase
Caltrans Jerry Claussenius (910) 908-2622   jerry.claussenius@dot.ca.gov
 
Corridor System Management Plan
Caltrans Jerry Claussenius (910) 908-2622   jerry.claussenius@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $2,730 $2,730
TLSP
$0 $5,545 $5,545
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$0 $50 $50
 
Total**** $0 $8,325 $8,325

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $2,392 $2,392 $-2,392
Design(PS&E)
$0 $0 $0 $2,284 $2,284 $-2,284
Right of Way
$0 $50 $50 $16 $16 $34
Construction
$0 $8,275 $8,275 $9,321 $9,321 $-1,046
 
Total* $0 $8,325 $8,325 $14,013 $14,013 $-5,688

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

02/22/2010 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

01/26/2011 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
 

 
 

 
04/25/2012 

07/22/2016 
04/25/2012 

07/22/2016 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
07/22/2017 

12/30/2016 
12/01/2017 

06/29/2018 
-4 

-18 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 20

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.