Route 46 Corridor Improvements (Whitley 2B) |
Description: Near Shandon, from 0.2 mile east of McMillan Canyon Road to 0.4 mile west of Lucy Brown Road.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo |
City | Shandon |
Zip Code | 93461 |
Senate District |
15 |
Assembly District | |
Congressional District | |
Caltrans District |
|
County/State Route | San Luis Obispo 46 |
Postmile Begin/End | 46 50.2 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
|||||
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $66,200 | $66,200 | ||||
Local** |
$0 | $9,500 | $9,500 | ||||
Total**** | $0 | $75,700 | $75,700 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $7,000 | $7,000 | $0 | $0 | $7,000 | |
Right of Way |
$0 | $13,500 | $13,500 | $-2 | $-2 | $13,502 | |
Construction |
$0 | $55,200 | $55,200 | $0 | $0 | $55,200 | |
Total* | $0 | $75,700 | $75,700 | $-2 | $-2 | $75,702 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/1998 05/01/2003 |
01/01/1998 05/01/2003 |
01/01/1998 05/01/2003 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/01/2011 08/01/2015 |
11/01/2011 08/01/2015 |
11/01/2011 08/01/2015 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
11/01/2012 05/01/2015 |
11/01/2012 05/01/2015 |
11/01/2012 05/01/2015 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2016 04/01/2018 |
03/01/2016 04/01/2018 |
03/01/2016 04/01/2018 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
100 | |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.