Route 46 Corridor Improvements (Whitley 2B)

Description: Near Shandon, from 0.2 mile east of McMillan Canyon Road to 0.4 mile west of Lucy Brown Road.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City Shandon
Zip Code 93461
 
Senate District
15
Assembly District
Congressional District
 
Caltrans District

 
 
County/State Route San Luis Obispo 46
Postmile Begin/End 46 50.2
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
Non-bond Funding
State/Federal*
$0 $66,200 $66,200
Local**
$0 $9,500 $9,500
 
Total**** $0 $75,700 $75,700

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $7,000 $7,000 $0 $0 $7,000
Right of Way
$0 $13,500 $13,500 $-2 $-2 $13,502
Construction
$0 $55,200 $55,200 $0 $0 $55,200
 
Total* $0 $75,700 $75,700 $-2 $-2 $75,702

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/1998 

05/01/2003 
01/01/1998 

05/01/2003 
01/01/1998 

05/01/2003 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2011 

08/01/2015 
11/01/2011 

08/01/2015 
11/01/2011 

08/01/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
11/01/2012 

05/01/2015 
11/01/2012 

05/01/2015 
11/01/2012 

05/01/2015 
 

 


Begin Construction Phase

End Construction Phase
03/01/2016 

04/01/2018 
03/01/2016 

04/01/2018 
03/01/2016 

04/01/2018 
 

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
100   

 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 0

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.