Caltrans Logo

Casitas Pass & Linden Ave interchanges

Description: In Carpinteria, from Carpinteria Creek Bridge to Linden Avenue. Reconstruct two interchanges (Casitas Pass Road and Linden Avenue) and extend Via Real frontage road.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Carpinteria
Zip Code 93013
 
Senate District
19
Assembly District
Congressional District
 
Caltrans District

 
 
County/State Route Santa Barbara 101
Postmile Begin/End 2.2 3.3
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (HOV)  0      
Lane Miles Added (Mixed)  0      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $25,417 $25,417
Non-bond Funding
State/Federal*
$0 $93,393 $93,393
Local**
$0 $700 $700
 
Total**** $0 $119,510 $119,510

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $6,770 $6,770 $0 $0 $6,770
Design(PS&E)
$0 $16,997 $16,997 $0 $0 $16,997
Right of Way
$0 $14,452 $14,452 $0 $0 $14,452
Construction
$0 $81,291 $81,291 $287 $287 $81,004
 
Total* $0 $119,510 $119,510 $287 $287 $119,223

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/24/2008 

07/20/2010 
 

 
04/24/2008 

07/20/2010 
100  04/24/2008 

07/20/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/20/2010 

08/01/2013 
 

 
07/20/2010 

08/01/2013 
100  07/20/2010 

12/30/2015 


-29 
Begin Right of Way Phase

End Right of Way Phase
04/01/2011 

07/15/2013 
 

 
04/01/2011 

07/15/2013 
100  04/01/2011 

12/30/2015 


-30 
Begin Construction Phase

End Construction Phase
12/01/2013 

12/01/2017 
 

 
12/01/2013 

12/01/2017 
100  06/20/2016 

01/20/2021 
-31 

-38 
Begin Closeout Phase

End Closeout Phase
12/01/2017 

11/01/2018 
 

 
12/01/2017 

11/01/2018 
50  01/20/2021 

08/01/2023 
-38 

-58 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 0

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.