Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Casitas Pass & Linden Ave interchanges |
Description: In Carpinteria, from Carpinteria Creek Bridge to Linden Avenue. Reconstruct two interchanges (Casitas Pass Road and Linden Avenue) and extend Via Real frontage road.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Barbara |
City | Carpinteria |
Zip Code | 93013 |
Senate District |
19 |
Assembly District | |
Congressional District | |
Caltrans District |
|
County/State Route | Santa Barbara 101 |
Postmile Begin/End | 2.2 3.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
|||||
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $25,417 | $25,417 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $93,393 | $93,393 | ||||
Local** |
$0 | $700 | $700 | ||||
Total**** | $0 | $119,510 | $119,510 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $6,770 | $6,770 | $0 | $0 | $6,770 | |
Design(PS&E) |
$0 | $16,997 | $16,997 | $0 | $0 | $16,997 | |
Right of Way |
$0 | $14,452 | $14,452 | $0 | $0 | $14,452 | |
Construction |
$0 | $81,291 | $81,291 | $287 | $287 | $81,004 | |
Total* | $0 | $119,510 | $119,510 | $287 | $287 | $119,223 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
04/24/2008 07/20/2010 |
|
04/24/2008 07/20/2010 |
100 | 04/24/2008 07/20/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/20/2010 08/01/2013 |
|
07/20/2010 08/01/2013 |
100 | 07/20/2010 12/30/2015 |
0 -29 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2011 07/15/2013 |
|
04/01/2011 07/15/2013 |
100 | 04/01/2011 12/30/2015 |
0 -30 |
Begin Construction Phase
End Construction Phase |
12/01/2013 12/01/2017 |
|
12/01/2013 12/01/2017 |
100 | 06/20/2016 01/20/2021 |
-31 -38 |
Begin Closeout Phase
End Closeout Phase |
12/01/2017 11/01/2018 |
|
12/01/2017 11/01/2018 |
50 | 01/20/2021 08/01/2023 |
-38 -58 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.