Road 80 - Ave 304 to Ave 328

Description: Between Visalia and Dinuba, on Road 80 Expressway from Avenue 304 to Avenue 328. Widen to 4 lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City
Zip Code
 
Senate District
16, 18
Assembly District 31, 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
 
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$7,855 $0 $7,855
Non-bond Funding
State/Federal*
$19,007 $0 $19,007
Local**
$3,400 $0 $3,400
 
Total**** $30,262 $0 $30,262

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$2,388 $0 $2,388 $0 $0 $2,388
Design(PS&E)
$4,307 $0 $4,307 $0 $0 $4,307
Right of Way
$12,712 $0 $12,712 $0 $0 $12,712
Construction
$10,855 $0 $10,855 $0 $0 $10,855
 
Total* $30,262 $0 $30,262 $0 $0 $30,262

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
 

 
 

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
 

 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.