TraPac Terminal Automation - Automated Shuttle Carrier Maintenance & Repair (M&R) Facility

Description: Automated Shuttle Carrier Maintenance & Repair (M&R) Facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code
 
Senate District
27
Assembly District 54
Congressional District 46
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Nbr New Structures Constructed  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Los Angeles Harbor Department (Port of Los Angeles) Cristina Sar 310-732-3627   csar@portla.org
Design (PS&E) Phase
City of Los Angeles Harbor Department (Port of Los Angeles) Cristina Sar 310-732-3627   csar@portla.org
Right of Way Phase
City of Los Angeles Harbor Department (Port of Los Angeles) Cristina Sar 310-732-3627   csar@portla.org
Construction Phase
City of Los Angeles Harbor Department (Port of Los Angeles) Cristina Sar 310-732-3627   csar@portla.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$2,840 $0 $2,840
Non-bond Funding
Local**
$2,840 $0 $2,840
 
Total**** $5,681 $0 $5,681

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$376 $0 $376 $2,454 $2,454 $-2,079
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,305 $0 $5,305 $6,757 $6,757 $-1,452
 
Total* $5,681 $0 $5,681 $9,212 $9,212 $-3,531

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/31/2003 

12/31/2007 
08/20/2014 

08/20/2014 
10/31/2003 

12/31/2007 
100  10/31/2003 

12/31/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/30/2012 

01/31/2015 
08/20/2014 

08/20/2014 
11/30/2012 

01/31/2015 
100  11/30/2012 

01/31/2015 


Begin Right of Way Phase

End Right of Way Phase
02/28/2014 

07/31/2014 
08/20/2014 

08/20/2014 
02/28/2014 

07/31/2014 
100  02/28/2014 

07/31/2014 


Begin Construction Phase

End Construction Phase
07/31/2015 

08/31/2016 
08/20/2014 

08/20/2014 
07/31/2015 

08/31/2016 
100  10/19/2015 

09/30/2017 
-3 

-13 
Begin Closeout Phase

End Closeout Phase
08/31/2016 

08/31/2017 
08/20/2014 

 
08/31/2016 

08/31/2017 
100  07/03/2017 

05/31/2018 
-10 

-9 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Nbr New Structures Constructed 1 1

Bond Funding Cost
Adopted:
$2,840,500
Current Approved:
$2,840,500
Actual Expenditures:
$2,840,500

 