Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Vincent Siding at CP Quartz and 2nd Platform at Vincent/Acton Grade Station |
Description: Extend existing siding, construct crossover
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | |
Zip Code | |
Senate District |
07 |
Assembly District | |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 11715 | 11715 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
SCRRA | Elizabeth Lun | 909-593-6419 | lune@scrra.net | |
Design (PS&E) Phase |
SCRRA | Elizabeth Lun | 909-593-6419 | lune@scrra.net | |
Right of Way Phase |
SCRRA | Elizabeth Lun | 909-593-6419 | lune@scrra.net | |
Construction Phase |
SCRRA | Elizabeth Lun | 909-593-6419 | lune@scrra.net | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$8,200 | $0 | $8,200 | ||||
Non-bond Funding | |||||||
Local** |
$9,200 | $0 | $9,200 | ||||
Total**** | $17,400 | $0 | $17,400 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$350 | $0 | $350 | $350 | $350 | $0 | |
Design(PS&E) |
$650 | $0 | $650 | $650 | $650 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$16,400 | $0 | $16,400 | $16,859 | $16,859 | $-459 | |
Total* | $17,400 | $0 | $17,400 | $17,859 | $17,859 | $-459 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2014 03/12/2014 |
12/10/2014 12/10/2014 |
01/01/2014 03/12/2014 |
100 | 03/12/2014 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/11/2013 03/27/2014 |
12/10/2014 12/10/2014 |
12/11/2013 03/27/2014 |
100 | 03/27/2014 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
12/10/2014 12/10/2014 |
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/30/2015 12/31/2016 |
12/10/2014 12/10/2014 |
04/30/2015 12/31/2016 |
100 | 05/15/2015 03/31/2017 |
0 -3 |
Begin Closeout Phase
End Closeout Phase |
01/01/2017 04/30/2017 |
12/10/2014 |
01/01/2017 04/30/2017 |
100 | 07/03/2017 06/30/2018 |
-6 -14 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Track Miles Layed | 11715 | 11715 |
Bond Funding Cost | |
---|---|
Adopted: |
$8,200,000 |
Current Approved: |
$8,200,000 |
Actual Expenditures: |
$8,200,000 |
Status as of December 31, 2023.