Caltrans Logo

Vincent Siding at CP Quartz and 2nd Platform at Vincent/Acton Grade Station

Description: Extend existing siding, construct crossover

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City
Zip Code
 
Senate District
07
Assembly District
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Additional Track Miles Layed  11715    11715  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SCRRA Elizabeth Lun 909-593-6419   lune@scrra.net
Design (PS&E) Phase
SCRRA Elizabeth Lun 909-593-6419   lune@scrra.net
Right of Way Phase
SCRRA Elizabeth Lun 909-593-6419   lune@scrra.net
Construction Phase
SCRRA Elizabeth Lun 909-593-6419   lune@scrra.net
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$8,200 $0 $8,200
Non-bond Funding
Local**
$9,200 $0 $9,200
 
Total**** $17,400 $0 $17,400

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$350 $0 $350 $350 $350 $0
Design(PS&E)
$650 $0 $650 $650 $650 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$16,400 $0 $16,400 $16,859 $16,859 $-459
 
Total* $17,400 $0 $17,400 $17,859 $17,859 $-459

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2014 

03/12/2014 
12/10/2014 

12/10/2014 
01/01/2014 

03/12/2014 
100   

03/12/2014 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/11/2013 

03/27/2014 
12/10/2014 

12/10/2014 
12/11/2013 

03/27/2014 
100   

03/27/2014 


Begin Right of Way Phase

End Right of Way Phase
 

 
12/10/2014 

12/10/2014 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/30/2015 

12/31/2016 
12/10/2014 

12/10/2014 
04/30/2015 

12/31/2016 
100  05/15/2015 

03/31/2017 


-3 
Begin Closeout Phase

End Closeout Phase
01/01/2017 

04/30/2017 
12/10/2014 

 
01/01/2017 

04/30/2017 
100  07/03/2017 

06/30/2018 
-6 

-14 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Track Miles Layed 11715 11715

Bond Funding Cost
Adopted:
$8,200,000
Current Approved:
$8,200,000
Actual Expenditures:
$8,200,000

 

Status as of December 31, 2023.