Install Ramp Metering at Various Locations

Description: In San Diego County, at various locations from Birmingham Drive to Vandegrift Boulevard. Install ramp metering. (Prop 1B Bond Funded Project)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City Encinitas, Oceanside
Zip Code 92007, 92024, 92054
 
Senate District
36
Assembly District 73
Congressional District 50
 
Caltrans District
11
 
 
County/State Route San Diego 5
Postmile Begin/End R  39.6 R  54.4
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  4    4  
Ramp Widenings      3  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Shahin Sepassi 858-518-3912   ssepassi@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Shahin Sepassi 858-518-3912   ssepassi@dot.ca.gov
Right of Way Phase
Department of Transportation Shahin Sepassi 858-518-3912   ssepassi@dot.ca.gov
Construction Phase
Department of Transportation Shahin Sepassi 858-518-3912   ssepassi@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Shahin Sepassi 858-518-3912   ssepassi@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$8,350 $-2,480 $5,870
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$0 $1,700 $1,700
Non Budgeted ETC
$0 $0 $0
 
Total**** $8,350 $-780 $7,570

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$500 $0 $500 $508
Design(PS&E)
$600 $0 $600 $1,302
Right of Way
$50 $0 $50 $1
Construction
$7,200 $-780 $6,420 $5,430
 
Total* $8,350 $-780 $7,570 $7,241

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2007 

03/01/2008 
 

 
04/01/2007 

03/01/2008 
100  05/11/2007 

03/14/2008 
-1 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2008 

12/01/2008 
 

 
03/01/2008 

12/01/2008 
100  04/15/2008 

03/31/2009 
-1 

-4 
Begin Right of Way Phase

End Right of Way Phase
04/01/2007 

03/01/2008 
 

 
04/01/2007 

03/01/2008 
100  06/29/2007 

01/07/2009 
-3 

-10 
Begin Construction Phase

End Construction Phase
06/01/2009 

03/01/2010 
 

 
06/01/2009 

03/01/2010 
04/20/2010 

06/05/2012 
-11 

-28 
Begin Closeout Phase

End Closeout Phase
03/01/2010 

05/01/2010 
 

 
03/01/2010 

05/01/2010 
100  06/05/2012 

07/10/2013 
-28 

-39 
????????
Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 4 4
Ramp Widenings 3

Bond Funding Cost
Adopted:
$8,350,000
Current Approved:
$6,373,500
Actual Expenditures:
$7,206,620

 

Status as of December 31, 2023.