Install Vehicle Detection Systems (VDS) |
Description: In San Diego County on Routes 5, 15, and 805. Install Vehicle Detection Systems (VDS). (Prop 1B Bond Funded Project)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | San Diego |
Zip Code | 92154 |
Senate District |
36, 38 |
Assembly District | 66, 73, 77 |
Congressional District | 50 |
Caltrans District |
11 |
County/State Route | San Diego 805 |
Postmile Begin/End | 0 28.8 |
County/State Route | San Diego 15 |
Postmile Begin/End | R 0.8 R 36.3 |
County/State Route | San Diego 5 |
Postmile Begin/End | R 19.8 R 58.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1 | |
Number of Stations / Number of Ramps Metered | 69 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Shahin Sepassi | (858) 518-3912 | shahin.sepassi@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Shahin Sepassi | (858) 518-3912 | shahin.sepassi@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Shahin Sepassi | (858) 518-3912 | shahin.sepassi@dot.ca.gov | |
Construction Phase |
Department of Transportation | Shahin Sepassi | (858) 518-3912 | shahin.sepassi@dot.ca.gov | |
Corridor System Management Plan |
Department of Transportation | Shahin Sepassi | (858) 518-3912 | shahin.sepassi@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$4,060 | $-10 | $4,050 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $10 | $10 | ||||
Total**** | $4,060 | $0 | $4,060 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$300 | $0 | $300 | $213 | |||
Design(PS&E) |
$300 | $0 | $300 | $502 | |||
Right of Way |
$30 | $0 | $30 | $0 | |||
Construction |
$3,430 | $0 | $3,430 | $2,001 | |||
Total* | $4,060 | $0 | $4,060 | $2,716 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2007 09/01/2007 |
|
06/01/2007 09/01/2007 |
100 | 09/04/2007 11/09/2007 |
-3 -2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2007 04/01/2008 |
|
09/01/2007 04/01/2008 |
100 | 10/22/2007 05/30/2008 |
-2 -2 |
Begin Right of Way Phase
End Right of Way Phase |
06/01/2007 04/01/2008 |
|
06/01/2007 04/01/2008 |
100 | 08/13/2007 04/02/2008 |
-2 0 |
Begin Construction Phase
End Construction Phase |
07/01/2008 02/01/2009 |
|
07/01/2008 02/01/2009 |
100 | 09/06/2008 05/29/2009 |
-2 -4 |
Begin Closeout Phase
End Closeout Phase |
02/01/2009 04/01/2009 |
|
02/01/2009 04/01/2009 |
100 | 06/01/2009 04/29/2010 |
-4 -13 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1 | |
Number of Stations / Number of Ramps Metered | 69 |
Bond Funding Cost | |
---|---|
Adopted: |
$4,060,000 |
Current Approved: |
$4,060,000 |
Actual Expenditures: |
$2,715,190 |
Status as of December 31, 2023.