San Diego - Upgrade material lab facility |
Description: In the city of San Diego, at the Kearney Mesa Material Lab (L5506). Upgrade material lab facility.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | San Diego |
Zip Code | 92111 |
Senate District |
39 |
Assembly District | 77 |
Congressional District | 52 |
Caltrans District |
11 |
County/State Route | San Diego 905 |
Postmile Begin/End | 9.6 11.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Bruce Lambert | (619) 688-3288 | Lambert, Bruce W@DOT | |
Design (PS&E) Phase |
Department of Transportation | Bruce Lambert | (619) 688-3288 | Lambert, Bruce W@DOT | |
Right of Way Phase |
Department of Transportation | Bruce Lambert | (619) 688-3288 | Lambert, Bruce W@DOT | |
Construction Phase |
Department of Transportation | Bruce Lambert | (619) 688-6689 | Lambert, Bruce W@DOT | |
Corridor System Management Plan |
Department of Transportation | Bruce Lambert | (619) 688-6689 | Lambert, Bruce W@DOT |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$5,695 | $-2,723 | $2,972 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $2,447 | $2,447 | ||||
Total**** | $5,695 | $-276 | $5,419 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$242 | $0 | $242 | $316 | |||
Design(PS&E) |
$1,280 | $0 | $1,280 | $1,272 | |||
Right of Way |
$5 | $0 | $5 | $0 | |||
Construction |
$4,168 | $-276 | $3,892 | $3,097 | |||
Total* | $5,695 | $-276 | $5,419 | $4,685 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/17/2007 02/22/2008 |
|
09/17/2007 02/29/2008 |
100 | 09/17/2007 02/29/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/23/2008 01/06/2010 |
|
03/03/2008 09/27/2013 |
100 | 03/03/2008 03/25/2013 |
0 6 |
Begin Right of Way Phase
End Right of Way Phase |
06/29/2010 |
|
06/29/2010 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/06/2010 11/02/2010 |
|
03/21/2014 04/24/2015 |
100 | 10/24/2013 01/06/2015 |
5 4 |
Begin Closeout Phase
End Closeout Phase |
11/02/2010 01/01/2011 |
|
04/24/2015 05/23/2016 |
100 | 01/06/2015 10/30/2015 |
4 7 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$5,695,000 |
Current Approved: |
$2,447,000 |
Actual Expenditures: |
$2,477,000 |
Status as of December 31, 2023.