San Diego - Upgrade material lab facility

Description: In the city of San Diego, at the Kearney Mesa Material Lab (L5506). Upgrade material lab facility.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City San Diego
Zip Code 92111
 
Senate District
39
Assembly District 77
Congressional District 52
 
Caltrans District
11
 
 
County/State Route San Diego 905
Postmile Begin/End 9.6 11.4
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Bruce Lambert (619) 688-3288   Lambert, Bruce W@DOT
Design (PS&E) Phase
Department of Transportation Bruce Lambert (619) 688-3288   Lambert, Bruce W@DOT
Right of Way Phase
Department of Transportation Bruce Lambert (619) 688-3288   Lambert, Bruce W@DOT
Construction Phase
Department of Transportation Bruce Lambert (619) 688-6689   Lambert, Bruce W@DOT
 
Corridor System Management Plan
Department of Transportation Bruce Lambert (619) 688-6689   Lambert, Bruce W@DOT
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$5,695 $-2,723 $2,972
Non-bond Funding
State/Federal*
$0 $2,447 $2,447
 
Total**** $5,695 $-276 $5,419

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$242 $0 $242 $316
Design(PS&E)
$1,280 $0 $1,280 $1,272
Right of Way
$5 $0 $5 $0
Construction
$4,168 $-276 $3,892 $3,097
 
Total* $5,695 $-276 $5,419 $4,685

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/17/2007 

02/22/2008 
 

 
09/17/2007 

02/29/2008 
100  09/17/2007 

02/29/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/23/2008 

01/06/2010 
 

 
03/03/2008 

09/27/2013 
100  03/03/2008 

03/25/2013 


Begin Right of Way Phase

End Right of Way Phase
06/29/2010 

 
 

 
06/29/2010 

 
100   

 


Begin Construction Phase

End Construction Phase
05/06/2010 

11/02/2010 
 

 
03/21/2014 

04/24/2015 
100  10/24/2013 

01/06/2015 


Begin Closeout Phase

End Closeout Phase
11/02/2010 

01/01/2011 
 

 
04/24/2015 

05/23/2016 
100  01/06/2015 

10/30/2015 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 1

Bond Funding Cost
Adopted:
$5,695,000
Current Approved:
$2,447,000
Actual Expenditures:
$2,477,000

 

Status as of December 31, 2023.