Construct auxiliary lanes.

Description: In San Marcos and Escondido, from Nordahl Road to Route 15/78 separation.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City Escondido, San Marcos
Zip Code 92027
 
Senate District
38
Assembly District 74
Congressional District 51
 
Caltrans District
11
 
 
County/State Route San Diego 78
Postmile Begin/End 15.5 R  16.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1041    1338  
Peak Period Time Savings (minutes)      80262  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation David Stebbins 619-688-6721   david.stebbins@dot.ca.gov
Design (PS&E) Phase
Department of Transportation David Stebbins 619-688-6721   david.stebbins@dot.ca.gov
Right of Way Phase
Department of Transportation David Stebbins 619-688-6721   david.stebbins@dot.ca.gov
Construction Phase
Department of Transportation David Stebbins 619-688-6721   david.stebbins@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$7,963 $-3,123 $4,840
Non-bond Funding
State/Federal*
$0 $200 $200
Local**
$0 $1,226 $1,226
 
Total**** $7,963 $-1,697 $6,266

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $545 $545 $546
Design(PS&E)
$0 $681 $681 $614
Right of Way
$290 $0 $290 $107
Construction
$7,673 $-2,923 $4,750 $3,213
 
Total* $7,963 $-1,697 $6,266 $4,480

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/18/2007 

03/11/2010 
 

 
11/18/2007 

03/11/2010 
100  11/18/2007 

03/11/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/11/2010 

08/01/2010 
 

 
03/11/2010 

08/01/2010 
100  03/11/2010 

08/11/2010 


Begin Right of Way Phase

End Right of Way Phase
03/11/2010 

07/01/2010 
 

 
03/11/2010 

07/01/2010 
100  03/11/2010 

06/14/2010 


Begin Construction Phase

End Construction Phase
01/01/2011 

09/01/2012 
 

 
01/01/2011 

09/01/2012 
100  05/05/2011 

03/22/2013 
-4 

-7 
Begin Closeout Phase

End Closeout Phase
09/01/2012 

12/01/2012 
 

 
09/01/2012 

12/01/2012 
100  03/23/2013 

07/18/2014 
-7 

-20 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1041 1338
Peak Period Time Savings (minutes) 80262

Bond Funding Cost
Adopted:
$7,963,000
Current Approved:
$7,963,000
Actual Expenditures:
$3,292,000

 

Status as of December 31, 2023.