Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
In El Centro Construct Maintenance Station |
Description: In El Centro, at the El Centro Maintenance Station (M5708) at 1102 Montenegro Way. Construct maintenance station.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Imperial |
City | El Centro |
Zip Code | 92243 |
Senate District |
40 |
Assembly District | 56 |
Congressional District | 51 |
Caltrans District |
11 |
County/State Route | Imperial - |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Harwell Ontoy | (619)688-3367 | harwell.ontoy@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Harwell Ontoy | (619)688-3367 | harwell.ontoy@dot.ca.gov | |
Right of Way Phase |
Caltrans | Harwell Ontoy | (619)688-3367 | harwell.ontoy@dot.ca.gov | |
Construction Phase |
Caltrans | Harwell Ontoy | (619)688-3367 | harwell.ontoy@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Harwell Ontoy | (619)688-3367 | harwell.ontoy@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
SHOPP Augmentation |
$19,960 | $-10,187 | $9,773 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $9,591 | $9,591 | ||||
Total**** | $19,960 | $-596 | $19,364 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,090 | $0 | $1,090 | $1,089 | |||
Design(PS&E) |
$3,051 | $0 | $3,051 | $3,482 | |||
Right of Way |
$3,946 | $-1,000 | $2,946 | $2,925 | |||
Construction |
$11,873 | $404 | $12,277 | $12,226 | |||
Total* | $19,960 | $-596 | $19,364 | $19,722 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
08/04/2008 06/28/2010 |
0 | 08/04/2008 06/28/2010 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
01/13/2014 |
0 | 01/13/2014 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
04/11/2014 08/30/2017 |
0 | 04/11/2014 06/29/2017 |
0 2 |
Begin Closeout Phase
End Closeout Phase |
|
|
08/30/2017 09/13/2018 |
0 | 08/30/2017 09/18/2018 |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Number of Stations / Number of Ramps Metered | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.