In El Centro Construct Maintenance Station

Description: In El Centro, at the El Centro Maintenance Station (M5708) at 1102 Montenegro Way. Construct maintenance station.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City El Centro
Zip Code 92243
 
Senate District
40
Assembly District 56
Congressional District 51
 
Caltrans District
11
 
 
County/State Route Imperial -
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Number of Stations / Number of Ramps Metered  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Harwell Ontoy (619)688-3367   harwell.ontoy@dot.ca.gov
Design (PS&E) Phase
Caltrans Harwell Ontoy (619)688-3367   harwell.ontoy@dot.ca.gov
Right of Way Phase
Caltrans Harwell Ontoy (619)688-3367   harwell.ontoy@dot.ca.gov
Construction Phase
Caltrans Harwell Ontoy (619)688-3367   harwell.ontoy@dot.ca.gov
 
Corridor System Management Plan
Caltrans Harwell Ontoy (619)688-3367   harwell.ontoy@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
SHOPP Augmentation
$19,960 $-10,187 $9,773
Non-bond Funding
State/Federal*
$0 $9,591 $9,591
 
Total**** $19,960 $-596 $19,364

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,090 $0 $1,090 $1,089
Design(PS&E)
$3,051 $0 $3,051 $3,482
Right of Way
$3,946 $-1,000 $2,946 $2,925
Construction
$11,873 $404 $12,277 $12,226
 
Total* $19,960 $-596 $19,364 $19,722

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
08/04/2008 

06/28/2010 
08/04/2008 

06/28/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

01/13/2014 
 

01/13/2014 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
04/11/2014 

08/30/2017 
04/11/2014 

06/29/2017 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
08/30/2017 

09/13/2018 
08/30/2017 

09/18/2018 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Number of Stations / Number of Ramps Metered 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.