Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
ACE: Avenue 66/UP Railroad Grade Separation Bypass |
Description: Construct two-lane roadway and elevated structure, connecting Avenue 66 westerly of Lincoln Street to Avenue 66 at Home Avenue.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Riverside |
City | Mecca |
Zip Code | 92254 |
Senate District |
28 |
Assembly District | 56 |
Congressional District | 36 |
Caltrans District |
08 |
County/State Route | Riverside N/A |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail/Highway At-Grade Crossings Eliminated | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Riverside County | John Ashlock | (951) 955-1511 | jashlock@rivco.org | |
Design (PS&E) Phase |
Riverside County | John Ashlock | (951) 955-1511 | jashlock@rivco.org | |
Right of Way Phase |
Riverside County | John Ashlock | (951) 955-1511 | jashlock@rivco.org | |
Construction Phase |
Riverside County | John Ashlock | (951) 955-1511 | jashlock@rivco.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$5,709 | $0 | $5,709 | ||||
Non-bond Funding | |||||||
State/Federal* |
$16,300 | $0 | $16,300 | ||||
Local** |
$17,071 | $0 | $17,071 | ||||
Total**** | $39,080 | $0 | $39,080 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$2,030 | $500 | $2,530 | $2,212 | $3,563 | $-1,033 | |
Design(PS&E) |
$1,350 | $1,000 | $2,350 | $5,422 | $5,422 | $-3,072 | |
Right of Way |
$3,000 | $-500 | $2,500 | $2,645 | $2,824 | $-324 | |
Construction |
$32,700 | $-1,000 | $31,700 | $46,934 | $48,295 | $-16,595 | |
Total* | $39,080 | $0 | $39,080 | $57,214 | $60,104 | $-21,024 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/26/2012 01/31/2016 |
08/17/2016 08/17/2016 |
07/26/2012 07/29/2017 |
100 | 10/05/2017 |
0 -2 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/25/2015 01/31/2016 |
08/17/2016 08/17/2016 |
12/30/2016 12/29/2017 |
100 | 10/06/2017 11/30/2019 |
-9 -23 |
Begin Right of Way Phase
End Right of Way Phase |
04/15/2015 03/15/2016 |
08/17/2016 08/17/2016 |
07/30/2017 07/29/2018 |
100 | 11/01/2017 12/31/2020 |
-3 -30 |
Begin Construction Phase
End Construction Phase |
12/08/2016 12/31/2019 |
08/17/2016 08/17/2016 |
07/30/2019 07/29/2021 |
100 | 05/11/2020 03/12/2022 |
-10 -8 |
Begin Closeout Phase
End Closeout Phase |
01/01/2020 05/30/2020 |
08/17/2016 |
07/30/2021 01/28/2022 |
0 | 03/13/2022 03/31/2024 |
-8 -26 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail/Highway At-Grade Crossings Eliminated | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.