Navy Drive Widening

Description: Widen from two to four lanes, from the State Route 4 Western Extension to Navy Drive connection to just west of the Navy Drive/Washington Street intersection.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Joaquin
City Stockton
Zip Code
 
Senate District

Assembly District
Congressional District
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1      
Roadway Modification (Lane Miles Modified)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Port of Stockton Juan Villanueva (209) 946-0246   jvillanueva@stocktonport.com
Design (PS&E) Phase
Port of Stockton Juan Villanueva (209) 946-0246   jvillanueva@stocktonport.com
Right of Way Phase
Port of Stockton Juan Villanueva (209) 946-0246   jvillanueva@stocktonport.com
Construction Phase
Port of Stockton Juan Villanueva (209) 946-0246   jvillanueva@stocktonport.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$2,000 $0 $2,000
Non-bond Funding
State/Federal*
$1,912 $0 $1,912
Local**
$2,901 $0 $2,901
 
Total**** $6,813 $0 $6,813

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$200 $0 $200 $0 $200 $0
Design(PS&E)
$650 $0 $650 $0 $650 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$5,963 $0 $5,963 $6,656 $6,656 $-693
 
Total* $6,813 $0 $6,813 $6,656 $7,506 $-693

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/27/2015 

12/05/2015 
 

 
04/27/2015 

12/05/2015 
100  04/27/2015 

12/05/2015 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/04/2015 

05/01/2016 
 

 
03/04/2015 

05/01/2016 
100  03/04/2015 

05/01/2016 


Begin Right of Way Phase

End Right of Way Phase
03/17/2015 

12/02/2015 
 

 
03/17/2015 

12/02/2015 
100  03/17/2015 

12/02/2015 


Begin Construction Phase

End Construction Phase
07/01/2016 

10/01/2017 
 

 
07/01/2016 

10/01/2017 
100  07/17/2017 

06/10/2019 
-13 

-21 
Begin Closeout Phase

End Closeout Phase
01/01/2018 

06/01/2018 
 

 
01/01/2018 

06/01/2018 
06/11/2019 

05/08/2023 
-18 

-60 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1
Roadway Modification (Lane Miles Modified) 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.