Caltrans Logo

I-80 Eastbound Cordelia Truck Scales Relocation

Description: Construct a Larger Truck Scale Facility

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Solano
City Fairfield
Zip Code
 
Senate District
05
Assembly District 08
Congressional District 10
 
Caltrans District
04
 
 
County/State Route Solano 80
Postmile Begin/End 13.3 15.7
Project Benefits
 Benefit Baseline Actual
New Truck Inspection Stations (Nbr Constructed)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Solano Transportation Authority Janet Adams (707) 424-6075   jadams@sta-snci.com
Design (PS&E) Phase
Solano Transportation Authority Janet Adams (707) 424-6075   jadams@sta-snci.com
Right of Way Phase
Caltrans Nicolas Endrawos (510) 286-5123   Nicolas.Endrawos@dot.ca.gov
Construction Phase
Caltrans Nicolas Endrawos (510) 286-5123   Nicolas.Endrawos@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$49,800 $-11,508 $38,292
LSR
$49,800 $-1,000 $48,800
Non-bond Funding
State/Federal*
$600 $0 $600
Local**
$700 $0 $700
 
Total**** $100,900 $-12,508 $88,392

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$5,800 $1,000 $6,800 $0 $0 $6,800
Design(PS&E)
$17,700 $-5,500 $12,200 $0 $0 $12,200
Right of Way
$3,000 $4,500 $7,500 $0 $0 $7,500
Construction
$74,400 $-12,508 $61,892 $0 $0 $61,892
 
Total* $100,900 $-12,508 $88,392 $0 $0 $88,392

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2003 

12/31/2009 
 

 
05/01/2003 

12/31/2009 
100  05/01/2003 

09/22/2010 


-9 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

05/01/2012 
 

 
01/01/2010 

05/01/2012 
100  01/01/2010 

03/18/2011 


14 
Begin Right of Way Phase

End Right of Way Phase
01/01/2010 

05/01/2012 
 

 
01/01/2010 

05/01/2012 
100  01/01/2010 

02/10/2011 


15 
Begin Construction Phase

End Construction Phase
10/01/2012 

12/31/2014 
01/25/2012 

 
08/31/2012 

12/31/2014 
100  01/25/2012 

03/24/2015 


-3 
Begin Closeout Phase

End Closeout Phase
01/01/2015 

12/31/2015 
 

 
01/01/2015 

12/31/2015 
03/24/2015 

11/30/2018 
-3 

-35 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
New Truck Inspection Stations (Nbr Constructed) 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.