I-80 Eastbound Cordelia Truck Scales Relocation |
Description: Construct a Larger Truck Scale Facility
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Solano |
City | Fairfield |
Zip Code | |
Senate District |
05 |
Assembly District | 08 |
Congressional District | 10 |
Caltrans District |
04 |
County/State Route | Solano 80 |
Postmile Begin/End | 13.3 15.7 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
New Truck Inspection Stations (Nbr Constructed) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Solano Transportation Authority | Janet Adams | (707) 424-6075 | jadams@sta-snci.com | |
Design (PS&E) Phase |
Solano Transportation Authority | Janet Adams | (707) 424-6075 | jadams@sta-snci.com | |
Right of Way Phase |
Caltrans | Nicolas Endrawos | (510) 286-5123 | Nicolas.Endrawos@dot.ca.gov | |
Construction Phase |
Caltrans | Nicolas Endrawos | (510) 286-5123 | Nicolas.Endrawos@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$49,800 | $-11,508 | $38,292 | ||||
LSR |
$49,800 | $-1,000 | $48,800 | ||||
Non-bond Funding | |||||||
State/Federal* |
$600 | $0 | $600 | ||||
Local** |
$700 | $0 | $700 | ||||
Total**** | $100,900 | $-12,508 | $88,392 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$5,800 | $1,000 | $6,800 | $0 | $0 | $6,800 | |
Design(PS&E) |
$17,700 | $-5,500 | $12,200 | $0 | $0 | $12,200 | |
Right of Way |
$3,000 | $4,500 | $7,500 | $0 | $0 | $7,500 | |
Construction |
$74,400 | $-12,508 | $61,892 | $0 | $0 | $61,892 | |
Total* | $100,900 | $-12,508 | $88,392 | $0 | $0 | $88,392 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/01/2003 12/31/2009 |
|
05/01/2003 12/31/2009 |
100 | 05/01/2003 09/22/2010 |
0 -9 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2010 05/01/2012 |
|
01/01/2010 05/01/2012 |
100 | 01/01/2010 03/18/2011 |
0 14 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2010 05/01/2012 |
|
01/01/2010 05/01/2012 |
100 | 01/01/2010 02/10/2011 |
0 15 |
Begin Construction Phase
End Construction Phase |
10/01/2012 12/31/2014 |
01/25/2012 |
08/31/2012 12/31/2014 |
100 | 01/25/2012 03/24/2015 |
7 -3 |
Begin Closeout Phase
End Closeout Phase |
01/01/2015 12/31/2015 |
|
01/01/2015 12/31/2015 |
0 | 03/24/2015 11/30/2018 |
-3 -35 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
New Truck Inspection Stations (Nbr Constructed) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.