Durfee Avenue Grade Separation Project

Description: Separate the roadway and the railroad tracks on Durfee Avenue in the City of Pico Rivera.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles
City Pico Rivera
Zip Code
 
Senate District
32
Assembly District 58
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Rail At-Grade Crossings Eliminated  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
ACE Construction Authority Rene Coronel (626)962-9292   rcoronel@sgvcog.org
Design (PS&E) Phase
ACE Construction Authority Rene Coronel (626)962-9292   rcoronel@sgvcog.org
Right of Way Phase
ACE Construction Authority Rene Coronel (626)962-9292   rcoronel@sgvcog.org
Construction Phase
ACE Construction Authority Rene Coronel (626)962-9292   rcoronel@sgvcog.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$2,620 $0 $2,620
LSR
$52,725 $0 $52,725
Non-bond Funding
State/Federal*
$18,478 $0 $18,478
Local**
$15,820 $0 $15,820
Private***
$1,500 $0 $1,500
 
Total**** $91,143 $0 $91,143

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$9,046 $0 $9,046 $9,265 $9,265 $-219
Right of Way
$32,624 $0 $32,624 $28,690 $28,690 $3,934
Construction
$49,473 $0 $49,473 $80,017 $87,032 $-37,559
 
Total* $91,143 $0 $91,143 $117,972 $124,987 $-33,844

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2013 

07/31/2014 
 

 
06/01/2013 

07/31/2014 
100  06/01/2013 

07/31/2014 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2012 

11/30/2017 
 

06/27/2018 
10/01/2012 

05/01/2018 
100  10/01/2012 

05/01/2018 


Begin Right of Way Phase

End Right of Way Phase
12/01/2014 

10/31/2017 
 

06/27/2018 
12/01/2014 

05/31/2018 
100  12/01/2014 

05/31/2018 


Begin Construction Phase

End Construction Phase
04/01/2018 

10/31/2020 
06/27/2018 

06/27/2018 
10/31/2018 

07/31/2021 
99  06/01/2019 

04/01/2024 
-7 

-32 
Begin Closeout Phase

End Closeout Phase
11/01/2020 

07/31/2021 
06/27/2018 

 
08/31/2021 

02/28/2022 
05/01/2024 

11/01/2024 
-32 

-33 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail At-Grade Crossings Eliminated 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.