Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Durfee Avenue Grade Separation Project |
Description: Separate the roadway and the railroad tracks on Durfee Avenue in the City of Pico Rivera.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Los Angeles |
City | Pico Rivera |
Zip Code | |
Senate District |
32 |
Assembly District | 58 |
Congressional District | 38 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
ACE Construction Authority | Rene Coronel | (626)962-9292 | rcoronel@sgvcog.org | |
Design (PS&E) Phase |
ACE Construction Authority | Rene Coronel | (626)962-9292 | rcoronel@sgvcog.org | |
Right of Way Phase |
ACE Construction Authority | Rene Coronel | (626)962-9292 | rcoronel@sgvcog.org | |
Construction Phase |
ACE Construction Authority | Rene Coronel | (626)962-9292 | rcoronel@sgvcog.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$2,620 | $0 | $2,620 | ||||
LSR |
$52,725 | $0 | $52,725 | ||||
Non-bond Funding | |||||||
State/Federal* |
$18,478 | $0 | $18,478 | ||||
Local** |
$15,820 | $0 | $15,820 | ||||
Private*** |
$1,500 | $0 | $1,500 | ||||
Total**** | $91,143 | $0 | $91,143 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$9,046 | $0 | $9,046 | $9,265 | $9,265 | $-219 | |
Right of Way |
$32,624 | $0 | $32,624 | $28,690 | $28,690 | $3,934 | |
Construction |
$49,473 | $0 | $49,473 | $80,017 | $87,032 | $-37,559 | |
Total* | $91,143 | $0 | $91,143 | $117,972 | $124,987 | $-33,844 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/2013 07/31/2014 |
|
06/01/2013 07/31/2014 |
100 | 06/01/2013 07/31/2014 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2012 11/30/2017 |
06/27/2018 |
10/01/2012 05/01/2018 |
100 | 10/01/2012 05/01/2018 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/01/2014 10/31/2017 |
06/27/2018 |
12/01/2014 05/31/2018 |
100 | 12/01/2014 05/31/2018 |
0 0 |
Begin Construction Phase
End Construction Phase |
04/01/2018 10/31/2020 |
06/27/2018 06/27/2018 |
10/31/2018 07/31/2021 |
99 | 06/01/2019 04/01/2024 |
-7 -32 |
Begin Closeout Phase
End Closeout Phase |
11/01/2020 07/31/2021 |
06/27/2018 |
08/31/2021 02/28/2022 |
0 | 05/01/2024 11/01/2024 |
-32 -33 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rail At-Grade Crossings Eliminated | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.