I-10 Corridor Express Lanes Contract 1

Description: implement two express lanes in each direction for a total of four general purpose and two express lanes in each direction with auxiliary lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Los Angeles, San Bernardino
City Los Angeles, San Bernardino
Zip Code
 
Senate District
20, 25
Assembly District 41, 52
Congressional District 27, 31, 35
 
Caltrans District
08
 
 
County/State Route San Bernardino 10
Postmile Begin/End 0 10
 
County/State Route Los Angeles 10
Postmile Begin/End 44.9 48.3
Project Benefits
 Benefit Baseline Actual
Additional Auxiliary Lane Miles  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
San Bernardino Associated Governments Chad Cosello (909)884-8276   ccostello@gosbcta.com
Design (PS&E) Phase
San Bernardino Associated Governments Chad Cosello (909)884-8276   ccostello@gosbcta.com
Right of Way Phase
San Bernardino Associated Governments Chad Cosello (909)884-8276   ccostello@gosbcta.com
Construction Phase
San Bernardino Associated Governments Chad Cosello (909)884-8276   ccostello@gosbcta.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$4,973 $0 $4,973
Non-bond Funding
State/Federal*
$281,500 $0 $281,500
Local**
$523,145 $0 $523,145
 
Total**** $809,618 $0 $809,618

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$6,903 $0 $6,903 $0 $0 $6,903
Design(PS&E)
$30,325 $0 $30,325 $0 $0 $30,325
Right of Way
$47,811 $0 $47,811 $0 $0 $47,811
Construction
$724,579 $0 $724,579 $0 $0 $724,579
 
Total* $809,618 $0 $809,618 $0 $0 $809,618

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2012 

07/06/2017 
 

 
09/01/2012 

07/06/2017 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2018 

11/01/2021 
 

 
07/01/2018 

11/01/2021 
100   

 


Begin Right of Way Phase

End Right of Way Phase
09/01/2017 

03/01/2022 
 

 
09/01/2017 

03/01/2022 
100   

 


Begin Construction Phase

End Construction Phase
07/01/2018 

02/01/2024 
 

 
07/01/2018 

02/01/2024 
 

 


Begin Closeout Phase

End Closeout Phase
02/02/2024 

02/02/2027 
 

 
02/02/2024 

02/02/2027 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Auxiliary Lane Miles 1

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.