Route 125/905 Connector |
Description: In and near San Diego at Route 25/905 separation
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Diego |
City | San Diego |
Zip Code | |
Senate District |
40 |
Assembly District | 80 |
Congressional District | 51 |
Caltrans District |
11 |
County/State Route | San Diego 125 |
Postmile Begin/End | 0.8 0.8 |
County/State Route | San Diego 905 |
Postmile Begin/End | 9.8 9.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Jacqueline Appleton-Deane | 619-688-2561 | jacqueline.appleton-deane@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Jacqueline Appleton-Deane | 619-688-2561 | jacqueline.appleton-deane@dot.ca.gov | |
Right of Way Phase |
Caltrans | Jacqueline Appleton-Deane | 619-688-2561 | jacqueline.appleton-deane@dot.ca.govjacqueline.appleton-deane@dot.ca.gov | |
Construction Phase |
Caltrans | Jacqueline Appleton-Deane | 619-688-2561 | jacqueline.appleton-deane@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$24 | $0 | $24 | ||||
Non-bond Funding | |||||||
Local** |
$5 | $0 | $5 | ||||
Total**** | $29 | $0 | $29 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $5 | $5 | $0 | $0 | $5 | |
Design(PS&E) |
$5 | $0 | $5 | $0 | $0 | $5 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$24 | $-5 | $19 | $0 | $0 | $19 | |
Total* | $29 | $0 | $29 | $0 | $0 | $29 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/30/2004 |
|
07/30/2004 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/11/2017 08/15/2019 |
|
08/11/2017 08/15/2019 |
50 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
09/11/2017 08/15/2019 |
|
09/11/2017 10/11/2019 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/02/2020 04/04/2022 |
|
08/17/2020 08/15/2022 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/04/2022 10/25/2024 |
|
02/21/2023 10/16/2025 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$26,000 |
Current Approved: |
$30,000 |
Actual Expenditures: |
$28,000 |
Status as of December 31, 2023.