Caltrans Logo

Route 125/905 Connector

Description: In and near San Diego at Route 25/905 separation

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Diego
City San Diego
Zip Code
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
 
County/State Route San Diego 125
Postmile Begin/End 0.8 0.8
 
County/State Route San Diego 905
Postmile Begin/End 9.8 9.8
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  1      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Jacqueline Appleton-Deane 619-688-2561   jacqueline.appleton-deane@dot.ca.gov
Design (PS&E) Phase
Caltrans Jacqueline Appleton-Deane 619-688-2561   jacqueline.appleton-deane@dot.ca.gov
Right of Way Phase
Caltrans Jacqueline Appleton-Deane 619-688-2561   jacqueline.appleton-deane@dot.ca.govjacqueline.appleton-deane@dot.ca.gov
Construction Phase
Caltrans Jacqueline Appleton-Deane 619-688-2561   jacqueline.appleton-deane@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$24 $0 $24
Non-bond Funding
Local**
$5 $0 $5
 
Total**** $29 $0 $29

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $5 $5 $0 $0 $5
Design(PS&E)
$5 $0 $5 $0 $0 $5
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$24 $-5 $19 $0 $0 $19
 
Total* $29 $0 $29 $0 $0 $29

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

07/30/2004 
 

 
 

07/30/2004 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/11/2017 

08/15/2019 
 

 
08/11/2017 

08/15/2019 
50   

 


Begin Right of Way Phase

End Right of Way Phase
09/11/2017 

08/15/2019 
 

 
09/11/2017 

10/11/2019 
 

 


Begin Construction Phase

End Construction Phase
03/02/2020 

04/04/2022 
 

 
08/17/2020 

08/15/2022 
 

 


Begin Closeout Phase

End Closeout Phase
04/04/2022 

10/25/2024 
 

 
02/21/2023 

10/16/2025 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) 1

Bond Funding Cost
Adopted:
$26,000
Current Approved:
$30,000
Actual Expenditures:
$28,000

 

Status as of December 31, 2023.