Metro Air Parkway Northbound Auxiliary Lane |
Description: On SAC 5 from 5/99 interchange to Metro Air Parkway interchange
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
Sacramento |
City | Sacramento |
Zip Code | |
Senate District |
06 |
Assembly District | 07 |
Congressional District | 10 |
Caltrans District |
03 |
County/State Route | Sacramento 5 |
Postmile Begin/End | 30.2 31.2 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 1 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Sacramento County | John Holder | 530-741-5448 | john.holder@dot.ca.gov | |
Design (PS&E) Phase |
Sacramento County | John Holder | 530-741-5448 | john.holder@dot.ca.gov | |
Right of Way Phase |
Sacramento County | John Holder | 530-741-5448 | john.holder@dot.ca.gov | |
Construction Phase |
Sacramento County | John Holder | 530-741-5448 | john.holder@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$2 | $0 | $2 | ||||
Non-bond Funding | |||||||
Local** |
$2 | $0 | $2 | ||||
Total**** | $4 | $0 | $4 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$1 | $0 | $1 | $0 | $0 | $1 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3 | $0 | $3 | $0 | $0 | $3 | |
Total* | $4 | $0 | $4 | $0 | $0 | $4 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/30/2020 |
|
03/30/2020 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/30/2020 05/01/2020 |
|
03/30/2020 05/01/2020 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
03/30/2020 05/01/2020 |
|
03/30/2020 05/01/2020 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
12/15/2020 12/15/2021 |
|
12/15/2020 12/15/2021 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/15/2021 12/15/2022 |
|
12/15/2021 12/15/2022 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.