Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
State Route 60/Central Avenue Interchange |
Description: In San Bernardino County, at SR-60 and Central Avenue in the City of Chino.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Bernardino |
City | Chino |
Zip Code | |
Senate District |
20 |
Assembly District | 52 |
Congressional District | 35 |
Caltrans District |
08 |
County/State Route | San Bernardino 60 |
Postmile Begin/End | R 2.1 R 2.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | .5 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
San Bernardino County Transportation Authority | Paul Melocoton | 909-884-8276 | pmelocoton@gosbcta.com | |
Design (PS&E) Phase |
San Bernardino County Transportation Authority | Paul Melocoton | 909-884-8276 | pmelocoton@gosbcta.com | |
Right of Way Phase |
San Bernardino County Transportation Authority | Paul Melocoton | 909-884-8276 | pmelocoton@gosbcta.com | |
Construction Phase |
San Bernardino County Transportation Authority | Paul Melocoton | 909-884-8276 | pmelocoton@gosbcta.com | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
TCIF |
$9 | $0 | $9 | ||||
Non-bond Funding | |||||||
Local** |
$24 | $0 | $24 | ||||
Total**** | $33 | $0 | $33 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$1 | $0 | $1 | $0 | $0 | $1 | |
Design(PS&E) |
$2 | $0 | $2 | $0 | $0 | $2 | |
Right of Way |
$1 | $0 | $1 | $0 | $0 | $1 | |
Construction |
$29 | $0 | $29 | $0 | $0 | $29 | |
Total* | $33 | $0 | $33 | $0 | $0 | $33 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
05/22/2016 10/17/2017 |
|
05/22/2016 10/17/2017 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/18/2017 06/15/2020 |
|
10/18/2017 06/15/2020 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
10/18/2017 06/05/2020 |
|
10/18/2017 06/05/2020 |
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/02/2020 04/27/2023 |
|
09/02/2020 04/27/2023 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/27/2023 10/28/2023 |
|
04/27/2023 10/28/2023 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Modified or Improved Interchanges (Nbr Modified) | .5 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.