State Route 60/Central Avenue Interchange

Description: In San Bernardino County, at SR-60 and Central Avenue in the City of Chino.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino
City Chino
Zip Code
 
Senate District
20
Assembly District 52
Congressional District 35
 
Caltrans District
08
 
 
County/State Route San Bernardino 60
Postmile Begin/End R  2.1 R  2.6
Project Benefits
 Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified)  .5      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
San Bernardino County Transportation Authority Paul Melocoton 909-884-8276   pmelocoton@gosbcta.com
Design (PS&E) Phase
San Bernardino County Transportation Authority Paul Melocoton 909-884-8276   pmelocoton@gosbcta.com
Right of Way Phase
San Bernardino County Transportation Authority Paul Melocoton 909-884-8276   pmelocoton@gosbcta.com
Construction Phase
San Bernardino County Transportation Authority Paul Melocoton 909-884-8276   pmelocoton@gosbcta.com
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$9 $0 $9
Non-bond Funding
Local**
$24 $0 $24
 
Total**** $33 $0 $33

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$1 $0 $1 $0 $0 $1
Design(PS&E)
$2 $0 $2 $0 $0 $2
Right of Way
$1 $0 $1 $0 $0 $1
Construction
$29 $0 $29 $0 $0 $29
 
Total* $33 $0 $33 $0 $0 $33

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/22/2016 

10/17/2017 
 

 
05/22/2016 

10/17/2017 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/18/2017 

06/15/2020 
 

 
10/18/2017 

06/15/2020 
 

 


Begin Right of Way Phase

End Right of Way Phase
10/18/2017 

06/05/2020 
 

 
10/18/2017 

06/05/2020 
 

 


Begin Construction Phase

End Construction Phase
09/02/2020 

04/27/2023 
 

 
09/02/2020 

04/27/2023 
 

 


Begin Closeout Phase

End Closeout Phase
04/27/2023 

10/28/2023 
 

 
04/27/2023 

10/28/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Modified or Improved Interchanges (Nbr Modified) .5

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.