LAVTA Upgrade & Improvements Project

Description: Capital projects designed to address rehabilitation, safety and modernization of LAVTA facilities and /or bus stops

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Livermore
Zip Code 94551
 
Senate District
07
Assembly District 16
Congressional District 15
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    2  
Reduced Operating/Maintenance Cost  10    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TAMARA EDWARDS (925) 455-7566   TEDWARDS@LAVTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $17 $17
PTMISEA-99314
$362 $0 $362
Non-bond Funding
 
Total**** $362 $17 $378

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$362 $17 $378 $378 $378 $0
 
Total* $362 $17 $378 $378 $378 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2014 

09/30/2014 
02/08/2017 

02/08/2017 
07/01/2015 

03/31/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2014 

03/31/2017 
06/28/2022 

06/28/2022 
06/30/2016 

05/31/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
03/31/2017 

06/30/2017 
06/28/2022 

06/28/2022 
05/01/2022 

06/25/2022 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 2
Reduced Operating/Maintenance Cost 10 5

Bond Funding Cost
Adopted:
$361,514
Current Approved:
$361,514
Actual Expenditures:
$361,514

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31