Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
2015 Purchase of Two Transit Vehicles |
|
Description: Replace two (2) transit service vehicles which have reached useful life.1 - Class D - El Dorado, 5-passenger, gas fueled, low-floor minivan. 2 - Class A Ford E-350 small bus, 9-passenger, gas fueled
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Sierra |
| City | Downieville |
| Zip Code | 95936 |
| Senate District |
01 |
| Assembly District | 01 |
| Congressional District | 01 |
| Caltrans District |
03 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduced Operating/Maintenance Cost | 5 | 5 |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
BRYAN DAVEY | (530) 289-3201 | BDAVEY@SIERRACOUNTY.CA.GOV |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $0 | $0 | ||||
| PTMISEA-99313 |
$17 | $0 | $17 | ||||
| Non-bond Funding | |||||||
| State/Federal* |
$0 | $100 | $100 | ||||
| Local** |
$0 | $1 | $1 | ||||
| Total**** | $17 | $101 | $117 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$17 | $101 | $117 | $117 | $117 | $0 | |
| Total* | $17 | $101 | $117 | $117 | $117 | $0 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/19/2015 05/19/2015 |
|
05/19/2015 05/19/2015 |
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/19/2015 05/19/2015 |
|
05/19/2015 05/19/2015 |
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/01/2015 01/01/2016 |
03/23/2017 03/23/2017 |
06/28/2016 01/20/2017 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2016 06/01/2016 |
03/23/2017 03/23/2017 |
01/20/2017 01/21/2017 |
100 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Reduced Operating/Maintenance Cost | 5 | 5 |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$16,746 |
| Current Approved: |
$16,746 |
| Actual Expenditures: |
$16,746 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31
