SBCOG/SBLTA Admin Office Move

Description: New location is 1,950 sq ft, centrally situated, closer to agency partners and more accessible to our riders. Space needs renos and improvements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Benito
City Hollister
Zip Code 95023
 
Senate District
17
Assembly District 29
Congressional District 18
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  15      
Reduced Operating/Maintenance Cost  17      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2024
b=c-a
Current Approved
(12/31/2024
c
Bond Funding
PTMISEA-Interest
$0 $301 $301
PTMISEA-99313
$0 $117 $117
Non-bond Funding
State/Federal*
$0 $118 $118
 
Total**** $0 $536 $536

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2024
b=c-a
Current Approved
(12/31/2024
c
Cost to Date**
(12/31/2024
d
Cost Forecast
(12/31/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $536 $536 $0 $0 $536
 
Total* $0 $536 $536 $0 $0 $536

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2024)
c
% Complete
(12/31/2024)
d
Schedule Forecast
(12/31/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/17/2024 

12/31/2024 
 

 
10/17/2024 

12/31/2024 
 

 


Begin Closeout Phase

End Closeout Phase
12/31/2024 

12/31/2024 
 

 
12/31/2024 

12/31/2024 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 15
Reduced Operating/Maintenance Cost 17

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31