Caltrans Logo

City of Dinuba - Purchase of Electronic Farebox Equipment & Related Components

Description: Purchase of Electronic Farebox Equipment & Related Components for the City of Dinuba

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Visalia
Zip Code 93291
 
Senate District
16, 18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  25    25  
Increased Ridership  25    25  
Reduced Emissions      10  
Reduced Operating/Maintenance Cost  25    25  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD TREE (559) 623-0423   RTREE@TULARECAG.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$4 $1 $5
PTMISEA-99313
$48 $0 $48
Non-bond Funding
 
Total**** $52 $1 $53

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$52 $1 $53 $53 $53 $0
 
Total* $52 $1 $53 $53 $53 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2022 

07/31/2022 
02/21/2023 

02/21/2023 
07/01/2022 

03/31/3023 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2022 

12/31/2022 
02/21/2023 

02/21/2023 
06/01/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25 25
Increased Ridership 25 25
Reduced Emissions 10
Reduced Operating/Maintenance Cost 25 25

Bond Funding Cost
Adopted:
$51,547
Current Approved:
$48,002
Actual Expenditures:
$48,002

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31