Description: Purchase 6 replacement Orion CNG buses and electric charging station.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Riverside |
City | Thousand Palms |
Zip Code | 92276 |
Senate District |
40 |
Assembly District | 80 |
Congressional District | 36 |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 20 | 20 |
Increased Ridership | 2 | 2 |
Reduced Emissions | 10 | 10 |
Reduced Operating/Maintenance Cost | 33 | 33 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
Shelia Hruby | (760) 343-3456 X1514 | shruby@SUNLINE.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $5 | $5 | ||||
PTMISEA-99313 |
$3,982 | $0 | $3,982 | ||||
PTMISEA-99314 |
$949 | $0 | $949 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $244 | $244 | ||||
Total**** | $4,931 | $248 | $5,180 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$4,931 | $248 | $5,180 | $5,180 | $5,180 | $0 | |
Total* | $4,931 | $248 | $5,180 | $5,180 | $5,180 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2017 12/31/2018 |
|
01/01/2017 12/31/2018 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/01/2019 06/30/2019 |
04/23/2019 02/20/2021 |
01/31/2020 07/15/2020 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 20 | 20 |
Increased Ridership | 2 | 2 |
Reduced Emissions | 10 | 10 |
Reduced Operating/Maintenance Cost | 33 | 33 |
Bond Funding Cost | |
---|---|
Adopted: |
$4,931,311 |
Current Approved: |
$4,931,311 |
Actual Expenditures: |
$4,931,311 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31