East-West Connector VISTA Bus Acquisition |
|
Description: Purchase one 45 ft over-the-road CARB compliant diesel motor coaches for intercity bus services.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
| Project Location | |
|---|---|
| County |
Ventura |
| City | Ventura |
| Zip Code | 93003 |
| Senate District |
19 |
| Assembly District | 37, 38, 44 |
| Congressional District | 24, 25, 26 |
| Caltrans District |
07 |
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 20 | |
| Increased Ridership | 5 | 100 |
| Reduced Operating/Maintenance Cost | 10 | |
| Project Contacts | Agency | Contact Person | Telephone | |
|---|---|---|---|---|
| PTMISEA |
JUDITH JOHNDUFF | (805) 642-1591 | JJOHNDUFF@GOVENTURA.ORG |
| Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
|||||
| Bond Funding | |||||||
| PTMISEA-Interest |
$0 | $0 | $0 | ||||
| PTMISEA-99313 |
$149 | $-12 | $137 | ||||
| Non-bond Funding | |||||||
| Local** |
$1,209 | $0 | $1,209 | ||||
| Total**** | $1,358 | $-12 | $1,346 | ||||
**** Totals may not add up exactly to column amounts due to rounding
| Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
|---|---|---|---|---|---|---|---|
| Adopted Program (06/07/07) a |
Approved Changes (06/30/2025 b=c-a |
Current Approved (06/30/2025 c |
Cost to Date** (06/30/2025 d |
Cost Forecast (06/30/2025 e |
Cost Variance f=c-e |
||
| Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
| Construction |
$1,358 | $-12 | $1,346 | $137 | $137 | $1,209 | |
| Total* | $1,358 | $-12 | $1,346 | $137 | $137 | $1,209 | |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
| Project Schedule Baseline Summary | ||||||
|---|---|---|---|---|---|---|
| (Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2025) c |
% Complete (06/30/2025) d |
Schedule Forecast (06/30/2025) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/08/2016 05/26/2017 |
|
01/01/2017 07/01/2017 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
05/26/2017 06/26/2017 |
09/07/2018 09/07/2018 |
11/01/2017 11/30/2017 |
100 | |
0 0 |
No map available at this time.
| Project Benefits | ||
|---|---|---|
| Benefit | Baseline | Actual |
| Increase System Reliability | 20 | |
| Increased Ridership | 5 | 100 |
| Reduced Operating/Maintenance Cost | 10 | |
| Bond Funding Cost | |
|---|---|
| Adopted: |
$148,804 |
| Current Approved: |
$137,207 |
| Actual Expenditures: |
$137,207 |
Status as of June 30, 2025.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31