CNG Replacement Buses

Description: Purchase 24 CNG replacement buses for more suitable for freeway speeds and more passenger capacity

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
30, 32
Assembly District 16, 18
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    100  
Increased Ridership  20      
Reduced Operating/Maintenance Cost  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEVE WOODS (661) 324-9874   SWOODS@GETBUS.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$1,200 $0 $1,200
Non-bond Funding
State/Federal*
$0 $11,520 $11,520
Local**
$0 $1,680 $1,680
 
Total**** $1,200 $13,201 $14,401

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,200 $13,201 $14,401 $14,401 $14,401 $0
 
Total* $1,200 $13,201 $14,401 $14,401 $14,401 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/31/2016 

03/05/2018 
02/05/2018 

03/05/2018 
02/05/2018 

03/05/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2020 

07/01/2020 
02/20/2020 

02/20/2020 
02/01/2019 

02/13/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 100
Increased Ridership 20
Reduced Operating/Maintenance Cost 15

Bond Funding Cost
Adopted:
$1,200,000
Current Approved:
$1,200,000
Actual Expenditures:
$1,200,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31