TTD-So. Shore Transit AVL System & Schedule Software |
Description: Purchase, install and configure Demand Response scheduling software.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Various |
City | Stateline, Nv |
Zip Code | 89449 |
Senate District |
01 |
Assembly District | 05 |
Congressional District | 04 |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 2 | 8 |
Reduced Operating/Maintenance Cost | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
JUDY WEBER | (775) 589-5203 | JWEBER@TRPA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $3 | $3 | ||||
PTMISEA-99313 |
$208 | $-144 | $64 | ||||
PTMISEA-99314 |
$20 | $4 | $24 | ||||
Non-bond Funding | |||||||
Total**** | $228 | $-137 | $91 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$228 | $-137 | $91 | $91 | $91 | $0 | |
Total* | $228 | $-137 | $91 | $91 | $91 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2015 09/01/2015 |
08/19/2015 01/03/2018 |
11/01/2015 01/31/2017 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/30/2015 12/01/2015 |
01/03/2018 06/14/2018 |
02/01/2017 11/30/2017 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 2 | 8 |
Reduced Operating/Maintenance Cost | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$227,921 |
Current Approved: |
$87,762 |
Actual Expenditures: |
$87,762 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31