Vacaville Intermodal Station

Description: Contruct a new Fairfield/Vacaville Train Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Solano
City Fairfield
Zip Code 94533
 
Senate District
03
Assembly District 11
Congressional District 03
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GEORGE HICKS (707) 428-7491   GHICKS@FAIRFIELD.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $36 $36
PTMISEA-99313
$1,260 $0 $1,260
Non-bond Funding
State/Federal*
$60,785 $0 $60,785
Local**
$15,897 $0 $15,897
 
Total**** $77,942 $36 $77,978

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$1,157 $0 $1,157 $0 $0 $1,157
Design(PS&E)
$6,610 $0 $6,610 $0 $0 $6,610
Right of Way
$996 $0 $996 $0 $0 $996
Construction
$69,179 $36 $69,215 $1,295 $1,295 $67,919
 
Total* $77,942 $36 $77,978 $1,295 $1,295 $76,682

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2009 

06/01/2010 
 

 
06/01/2009 

06/01/2010 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/20/2009 

06/15/2014 
 

02/24/2017 
10/20/2009 

06/30/2014 
100   

 


Begin Right of Way Phase

End Right of Way Phase
12/15/2009 

02/11/2014 
 

 
12/15/2009 

02/11/2014 
100   

 


Begin Construction Phase

End Construction Phase
12/02/2014 

11/01/2016 
02/24/2017 

02/24/2017 
03/12/2015 

08/31/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2016 

03/01/2017 
05/04/2018 

05/04/2018 
12/31/2017 

04/30/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10

Bond Funding Cost
Adopted:
$1,259,623
Current Approved:
$1,259,623
Actual Expenditures:
$1,259,623

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31