Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Vine Transit CAD/AVL System |
Description: Will deploy a state-of-the-art Automatic Vehicle Location (AVL) System and Computer-Aided Dispatch(CAD) for fixed route and demand respo0nse fleets of vehicles
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Napa |
City | Napa |
Zip Code | 94559 |
Senate District |
07 |
Assembly District | 02 |
Congressional District | 01 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 | 20 |
Reduced Operating/Maintenance Cost | 20 | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
ANTONIO ONORATO | (707) 259-8779 | AONORATO@NCTPA.NET |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $5 | $5 | ||||
PTMISEA-99313 |
$400 | $214 | $614 | ||||
PTMISEA-99314 |
$97 | $0 | $97 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,449 | $-1,357 | $92 | ||||
Local** |
$0 | $1,446 | $1,446 | ||||
Total**** | $1,946 | $308 | $2,254 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,946 | $308 | $2,254 | $2,254 | $2,254 | $0 | |
Total* | $1,946 | $308 | $2,254 | $2,254 | $2,254 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/01/2014 09/01/2014 |
07/07/2016 07/07/2016 |
12/31/2014 03/31/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2015 12/31/2015 |
07/07/2016 07/07/2016 |
05/01/2016 06/30/2016 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 | 20 |
Reduced Operating/Maintenance Cost | 20 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$497,077 |
Current Approved: |
$711,014 |
Actual Expenditures: |
$711,014 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31