Caltrans Logo

Replacement Transit Buses

Description: Replacement of 4 35ft buses that have reached their end of useful life

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Union City
Zip Code 94587
 
Senate District
10
Assembly District 20
Congressional District 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
WILSON LEE (510) 675-5409   WILSON@UNIONCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$212 $0 $212
PTMISEA-99314
$93 $0 $93
Non-bond Funding
State/Federal*
$1,557 $169 $1,726
Local**
$227 $-102 $126
 
Total**** $2,089 $68 $2,157

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,089 $68 $2,157 $2,157 $2,157 $0
 
Total* $2,089 $68 $2,157 $2,157 $2,157 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2014 

03/31/2016 
 

 
09/01/2014 

03/31/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2016 

05/31/2016 
08/01/2016 

08/01/2016 
05/01/2016 

06/01/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 20

Bond Funding Cost
Adopted:
$304,538
Current Approved:
$304,538
Actual Expenditures:
$304,538

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31