Front Street Park-n-Ride Lot Expansion - Phase II

Description: Construct additional park-and-ride parking stalls along Front Street along with sidewalks, lighting and drainage improvements to serve the Rocklin Multimodal Station.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
01, 04
Assembly District 06
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    5  
Reduced Emissions  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4030   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $6 $6
PTMISEA-99313
$470 $0 $470
Non-bond Funding
 
Total**** $470 $6 $476

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$470 $6 $476 $476 $476 $0
 
Total* $470 $6 $476 $476 $476 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2014 

08/01/2014 
 

 
06/01/2014 

08/01/2014 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/30/2014 

09/01/2014 
 

 
08/30/2014 

09/01/2014 
 

 


Begin Right of Way Phase

End Right of Way Phase
04/01/2014 

06/01/2014 
 

 
04/01/2014 

06/01/2014 
 

 


Begin Construction Phase

End Construction Phase
04/01/2015 

08/01/2015 
09/05/2018 

09/05/2018 
03/30/2016 

05/15/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

10/01/2015 
09/05/2018 

09/05/2018 
05/15/2018 

06/30/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 5
Reduced Emissions 5 5

Bond Funding Cost
Adopted:
$469,983
Current Approved:
$469,983
Actual Expenditures:
$469,983

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31