Positive Train Control

Description: Implementing positive train control technology along the LOSSAN rail corridor

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City Oceanside
Zip Code 92054
 
Senate District
36, 39, 40
Assembly District 36, 39, 40
Congressional District 50, 51, 52, 53
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    25  
Reduced Operating/Maintenance Cost  6      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CHENXIA LI (760) 967-2818   CLI@NCTD.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$102 $0 $102
PTMISEA-99314
$1,343 $0 $1,343
Non-bond Funding
State/Federal*
$4,909 $78,049 $82,957
Local**
$0 $1,524 $1,524
 
Total**** $6,354 $79,574 $85,928

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$6,354 $79,574 $85,928 $70,404 $70,404 $15,524
 
Total* $6,354 $79,574 $85,928 $70,404 $70,404 $15,524

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2009 

08/30/2014 
 

08/20/2015 
06/01/2009 

08/01/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2011 

04/15/2014 
08/20/2015 

08/20/2015 
10/01/2009 

02/26/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/15/2012 

12/15/2014 
08/20/2015 

07/07/2016 
08/05/2011 

07/31/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
06/15/2016 

10/15/2016 
03/07/2019 

03/07/2019 
01/31/2019 

03/29/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 25
Reduced Operating/Maintenance Cost 6

Bond Funding Cost
Adopted:
$1,445,473
Current Approved:
$1,445,473
Actual Expenditures:
$1,445,473

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31