Caltrans Logo

ACE Electronic Fare Collection Project

Description: Would immediately validate tickets used on board and allow On-Board ticket sales with real time validation of credit card sales

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05
Assembly District 17
Congressional District 10, 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20      
Increased Ridership  3      
Reduced Operating/Maintenance Cost  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BRIAN SCHMIDT (209) 944-6241   BRIAN@ACERAIL.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$249 $-218 $31
Non-bond Funding
State/Federal*
$0 $92 $92
 
Total**** $249 $-126 $124

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $92 $92 $92 $92 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$249 $-218 $31 $31 $31 $0
 
Total* $249 $-126 $124 $124 $124 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2014 

12/31/2014 
10/29/2019 

10/29/2019 
03/01/2018 

09/01/2018 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2015 

12/31/2015 
10/29/2019 

10/29/2019 
10/31/2018 

04/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
12/31/2015 

03/31/2016 
10/29/2019 

10/29/2019 
10/01/2019 

10/30/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Increased Ridership 3
Reduced Operating/Maintenance Cost 1

Bond Funding Cost
Adopted:
$249,346
Current Approved:
$31,429
Actual Expenditures:
$31,429

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31