Golden Empire Transit Bus Stop Improvements

Description: Make ADA improvements to heavily used existing GET Bus Stops throughout metropolitan Bakersfield.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
16
Assembly District 34
Congressional District 23
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      30  
Increased Ridership  1    1  
Reduced Emissions      1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BOB SNODDY (661) 861-2191   BSNODDY@KERNCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $13 $13
PTMISEA-99313
$600 $-39 $561
Non-bond Funding
 
Total**** $600 $-26 $574

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$600 $-26 $574 $574 $574 $0
 
Total* $600 $-26 $574 $574 $574 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/2014 

12/31/2014 
09/03/2015 

09/03/2015 
06/01/2015 

08/31/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2015 

06/30/2015 
09/03/2015 

09/03/2015 
07/01/2015 

08/31/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/01/2015 

05/01/2015 
 

 
02/01/2015 

05/01/2015 
100   

 


Begin Construction Phase

End Construction Phase
08/01/2015 

12/31/2015 
05/24/2016 

08/25/2020 
10/01/2015 

04/01/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2016 

02/28/2016 
08/25/2020 

03/11/2021 
08/23/2020 

02/26/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30
Increased Ridership 1 1
Reduced Emissions 1

Bond Funding Cost
Adopted:
$600,000
Current Approved:
$560,998
Actual Expenditures:
$560,998

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31