Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Construct Park-and-Ride |
Description: Construct Park & Ride facility corner of BearMountainBlvd & PlumtreeDr in City of Arvin
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern |
City | Bakersfield |
Zip Code | 93309 |
Senate District |
16 |
Assembly District | 30 |
Congressional District | 22 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 20 | 20 |
Reduced Emissions | 10 | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
MIGUEL BARCENAS | (661) 204-3707 | MIGUELB@QUADKNOPF.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
LSR |
$64 | $-64 | $0 | ||||
PTMISEA-Interest |
$0 | $18 | $18 | ||||
PTMISEA-99313 |
$500 | $0 | $500 | ||||
PTMISEA-99314 |
$0 | $5 | $5 | ||||
Non-bond Funding | |||||||
Local** |
$50 | $-50 | $0 | ||||
Total**** | $614 | $-90 | $524 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$25 | $-25 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$25 | $-25 | $0 | $43 | $43 | $-43 | |
Right of Way |
$50 | $-50 | $0 | $240 | $240 | $-240 | |
Construction |
$514 | $10 | $524 | $241 | $241 | $283 | |
Total* | $614 | $-90 | $524 | $524 | $524 | $-0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
02/01/2015 03/01/2015 |
|
12/01/2016 12/01/2017 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/01/2015 03/31/2015 |
|
03/01/2015 03/31/2015 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
04/14/2016 04/14/2016 |
03/01/2015 10/01/2017 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/01/2015 07/31/2015 |
05/11/2020 05/11/2020 |
10/01/2019 03/01/2020 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/01/2015 10/31/2015 |
05/11/2020 05/11/2020 |
03/01/2020 05/01/2020 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 20 | 20 |
Reduced Emissions | 10 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$564,000 |
Current Approved: |
$505,405 |
Actual Expenditures: |
$505,405 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31