Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Solar Energy Installation-Transit Bldg Park & Ride |
Description: Install Solar Panels at the Transit Building Park & Ride station
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern |
City | Bakersfield |
Zip Code | 93309 |
Senate District |
16 |
Assembly District | 30 |
Congressional District | 22 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Emissions | 10 | 100 |
Reduced Operating/Maintenance Cost | 20 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
MIGUEL BARCENAS | (661) 204-3707 | MIGUELB@QUADKNOPF.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$127 | $-27 | $100 | ||||
PTMISEA-99314 |
$8 | $-8 | $0 | ||||
Non-bond Funding | |||||||
Total**** | $135 | $-35 | $100 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$135 | $-35 | $100 | $100 | $100 | $0 | |
Total* | $135 | $-35 | $100 | $100 | $100 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
10/01/2015 11/01/2015 |
07/09/2019 07/09/2019 |
05/17/2017 07/14/2017 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
11/01/2015 11/30/2015 |
07/09/2019 07/09/2019 |
05/17/2017 07/14/2017 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2016 02/28/2016 |
07/09/2019 07/09/2019 |
07/05/2017 07/14/2017 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/01/2016 04/30/2016 |
07/09/2019 07/09/2019 |
12/31/2017 12/31/2018 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Emissions | 10 | 100 |
Reduced Operating/Maintenance Cost | 20 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$134,793 |
Current Approved: |
$99,893 |
Actual Expenditures: |
$99,893 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31