Solar Energy Installation-Transit Bldg Park & Ride

Description: Install Solar Panels at the Transit Building Park & Ride station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93309
 
Senate District
16
Assembly District 30
Congressional District 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  10    100  
Reduced Operating/Maintenance Cost  20    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MIGUEL BARCENAS (661) 204-3707   MIGUELB@QUADKNOPF.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$127 $-27 $100
PTMISEA-99314
$8 $-8 $0
Non-bond Funding
 
Total**** $135 $-35 $100

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$135 $-35 $100 $100 $100 $0
 
Total* $135 $-35 $100 $100 $100 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2015 

11/01/2015 
07/09/2019 

07/09/2019 
05/17/2017 

07/14/2017 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2015 

11/30/2015 
07/09/2019 

07/09/2019 
05/17/2017 

07/14/2017 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2016 

02/28/2016 
07/09/2019 

07/09/2019 
07/05/2017 

07/14/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2016 

04/30/2016 
07/09/2019 

07/09/2019 
12/31/2017 

12/31/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 10 100
Reduced Operating/Maintenance Cost 20 5

Bond Funding Cost
Adopted:
$134,793
Current Approved:
$99,893
Actual Expenditures:
$99,893

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31