Caltrans Logo

Dial-a-Ride Fare Boxes & Security Cameras

Description: Install fare boxes and security cameras in the current fleet of dial-a-ride buses and for bus stops at California City Blvd and Senior Center

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City California City
Zip Code 93505
 
Senate District
18
Assembly District 36
Congressional District 23
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
WILLIAM T. WEIL (760) 373-7140   CITYMGR@CALIFORNIACITY.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$84 $-50 $33
PTMISEA-99314
$3 $0 $3
Non-bond Funding
 
Total**** $86 $-50 $36

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$86 $-50 $36 $36 $36 $-0
 
Total* $86 $-50 $36 $36 $36 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2015 

05/01/2015 
 

 
04/01/2015 

05/01/2015 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2015 

07/31/2015 
 

 
05/01/2015 

07/31/2015 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2015 

09/30/2015 
03/06/2016 

03/06/2016 
08/01/2016 

09/30/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2015 

12/31/2015 
10/23/2019 

10/23/2019 
10/01/2019 

10/15/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10

Bond Funding Cost
Adopted:
$86,198
Current Approved:
$35,842
Actual Expenditures:
$35,842

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31