Electric Buses/Replacement of CNG Bus & Trans Track

Description: Purchase Replacement CNG Vehicles (Buses) and convert fleet into electric buses. These buses will upgrade many onboard systems while also implementing data management of a Trans Track system.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
30, 32
Assembly District 16, 18
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      24  
Reduced Operating/Maintenance Cost  40    35  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEVEN WOODS (661) 324-9874   SWOODS@GETBUS.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $5 $5
PTMISEA-99313
$3,045 $-1,357 $1,688
PTMISEA-99314
$549 $-147 $402
Non-bond Funding
 
Total**** $3,594 $-1,499 $2,094

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,594 $-1,499 $2,094 $2,094 $2,094 $0
 
Total* $3,594 $-1,499 $2,094 $2,094 $2,094 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2014 

03/31/2015 
 

 
11/01/2014 

03/31/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2016 

05/01/2016 
 

 
01/01/2016 

05/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
05/15/2016 

07/01/2016 
03/09/2020 

03/09/2020 
12/03/2019 

01/08/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 24
Reduced Operating/Maintenance Cost 40 35

Bond Funding Cost
Adopted:
$3,593,896
Current Approved:
$2,089,755
Actual Expenditures:
$2,089,755

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31